Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 Jan 2024 | E bill submitted | Vytilla Section AE - 1 | |
03 Jan 2024 | E bill submitted | Vytilla Section AE - 1 | |
26 Dec 2023 | Work completed | Vytilla Section AE - 1 | |
23 Dec 2023 | GDB laying in progress | Vytilla Section AE - 1 | |
21 Dec 2023 | GDB laying in progress | Vytilla Section AE - 1 | |
14 Dec 2023 | Pipe laying completed | Vytilla Section AE - 1 | |
12 Dec 2023 | Pipe laying in progress | Vytilla Section AE - 1 | |
11 Dec 2023 | Pipe laying in progress | Vytilla Section AE - 1 | |
08 Dec 2023 | Pipe laying in progress | Vytilla Section AE - 1 | |
06 Dec 2023 | Pipe laying in progress | Vytilla Section AE - 1 |