| 08 Apr 2025 | Work in progress. 160 mm 10 Kg/Cm2-2650.5 m, 140 mm 10 Kg/Cm2-942m, 110 mm 10 Kg/Cm2- 3037.5 m, 90 mm 10 Kg/Cm2-5000 m, 75 mm 10 Kg/Cm2-3170 m, FHTC- 160, HTC-12 | Kolachery PH Sn AE | |
| 02 Apr 2025 | Work in progress. 160 mm 10 Kg/Cm2-2650.5 m, 140 mm 10 Kg/Cm2-942m, 110 mm 10 Kg/Cm2- 3037.5 m, 90 mm 10 Kg/Cm2-5000 m, 75 mm 10 Kg/Cm2-3170 m, FHTC- 135, HTC-19 | Kolachery PH Sn AE | |
| 28 Mar 2025 | Work in progress. 160 mm 10 Kg/Cm2-2644.5 m, 140 mm 10 Kg/Cm2-820 m, 110 mm 10 Kg/Cm2- 2374.5 m, 90 mm 10 Kg/Cm2-4785.5 m, 75 mm 10 Kg/Cm2-696 m, FHTC- 135, HTC-19 | Kolachery PH Sn AE | |
| 20 Mar 2025 | Work in progress. 160 mm 10 Kg/Cm2-2644.5 m, 140 mm 10 Kg/Cm2-820 m, 110 mm 10 Kg/Cm2- 2374.5 m, 90 mm 10 Kg/Cm2-4785.5 m, 75 mm 10 Kg/Cm2-696 m, FHTC- 135, HTC-19 | Kolachery PH Sn AE | |
| 14 Mar 2025 | Work in progress. 160 mm 10 Kg/Cm2-2644.5 m, 140 mm 10 Kg/Cm2-820 m, 110 mm 10 Kg/Cm2- 2374.5 m, 90 mm 10 Kg/Cm2-4785.5 m, 75 mm 10 Kg/Cm2-696 m, FHTC- 126, HTC-21 | Kolachery PH Sn AE | |
| 11 Mar 2025 | Work in progress. 160 mm 10 Kg/Cm2-2644.5 m, 140 mm 10 Kg/Cm2-820 m, 110 mm 10 Kg/Cm2- 2374.5 m, 90 mm 10 Kg/Cm2-4785.5 m, 75 mm 10 Kg/Cm2-696 m, FHTC- 98, HTC-14 | Kolachery PH Sn AE | |
| 27 Feb 2025 | Work in progress. 160 mm 10 Kg/Cm2-2644.5 m, 140 mm 10 Kg/Cm2-820 m, 110 mm 10 Kg/Cm2- 2374.5 m, 90 mm 10 Kg/Cm2-4785.5 m, 75 mm 10 Kg/Cm2-696 m, FHTC- 98, HTC-14 | Kolachery PH Sn AE | |
| 24 Feb 2025 | Work in progress. 160 mm 10 Kg/Cm2-2644.5 m, 140 mm 10 Kg/Cm2-820 m, 110 mm 10 Kg/Cm2- 2374.5 m, 90 mm 10 Kg/Cm2-4785.5 m, 75 mm 10 Kg/Cm2-516 m, FHTC- 95 | Kolachery PH Sn AE | |
| 20 Feb 2025 | Work in progress. 160 mm 10 Kg/Cm2-1380 m, 110 mm 10 Kg/Cm2- 1032 m, 90 mm 10 Kg/Cm2-2718 m, 75 mm 10 Kg/Cm2-516 m, FHTC-86 | Kolachery PH Sn AE | |
| 14 Feb 2025 | Work in progress. 160 mm 10 Kg/Cm2-1380 m, 110 mm 10 Kg/Cm2- 1032 m, 90 mm 10 Kg/Cm2-2718 m, 75 mm 10 Kg/Cm2-516 m | Kolachery PH Sn AE |