Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Aug 2022 | work completed and final bill submitted | Aryanad AE | |
23 Apr 2021 | Valve chamber to be constructed | Aruvikkara HW Dn EE | |
05 Apr 2021 | pipelaying and shifting of water connection works is completed. Valve chamber work is pending | Aruvikkara HW Dn EE | |
01 Apr 2021 | Only 100 mtrs of pipe laying work is to be done. | Aruvikkara HW Dn EE | |
27 Mar 2021 | Shifting of water supply connection and branch lines are over.Only 200 m of pipe laying work is balance | Aruvikkara HW Dn EE | |
18 Mar 2021 | 2800 m of pipe laying work is over and also shifting of existing connections are going on | Aruvikkara HW Dn EE | |
09 Mar 2021 | 2710 m of pipe laying work is over balance work is progressing | Aruvikkara HW Dn EE | |
24 Feb 2021 | 2510 m of pipe laying work is over balance work is progressing | Aruvikkara HW Dn EE | |
09 Feb 2021 | 2360 m of pipe laying work is over | Aruvikkara HW Dn EE | |
26 Jan 2021 | 2000 m of pipe laying work is over | Aruvikkara HW Dn EE |