Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Nov 2022 | work completed. | Malappuram Project Dn AE5 | |
17 Nov 2022 | Pipes laying works in progress. | Malappuram Project Dn AE5 | |
17 Oct 2022 | Pipes laying works in progress. | Malappuram Project Dn AE5 | |
07 Oct 2022 | Pipes laying works in progress. | Malappuram Project Dn AE5 | |
28 Sep 2022 | Pipes laying works in progress. | Malappuram Project Dn AE5 | |
09 Sep 2022 | 32 % - Pipes laying works in progress. | Malappuram Project Dn AE5 | |
29 Aug 2022 | Pipes laying works in progress. | Malappuram Project Dn AE5 | |
25 Aug 2022 | Pipes arrived and laying works in progress. | Malappuram Project Dn AE5 | |
20 Aug 2022 | Supply order placed for PVC Pipes. | Malappuram Project Dn AE5 | |
10 Aug 2022 | Supply order placed for PVC Pipes. | Malappuram Project Dn AE5 |