Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Aug 2021 | Trial running completed by 16.07.2021 | Kattappana Project Dn EE | |
19 Jul 2021 | Trial running started | Kattappana Project Dn EE | |
07 Jul 2021 | All the packages under this work are completed | Kattappana Project Dn EE | |
01 Jun 2021 | Electric Connection to be obtained for commissioning the scheme | Kattappana Project Dn EE | |
14 May 2021 | OHSR complete.Pump house completed.Pump set erected.Pressure filter connection works in progress.Application for electric connection submitted | Kattappana Project Dn EE | |
18 Mar 2021 | OHSR Structure completed.Interconnection works in progress | Kattappana Project Dn EE | |
25 Jan 2021 | OHSR Columns up to Base Slab Completed | Kattappana Project Dn EE | |
23 Dec 2020 | Laying of Pumping Main (1500m) Completed. Laying of Distribution 1000m out of 1800m Completed. OHSR First Brace Completed. Tender for Raw Water Pumps invited. | Kattappana Project Dn EE | |
18 Dec 2020 | Over all 75% Completed | Kattappana Project Dn EE | |
23 Nov 2020 | Laying of pumping and distribution mains started | Kattappana Project Dn EE |