Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 Aug 2021 Trial running completed by 16.07.2021 Kattappana Project Dn EE
19 Jul 2021 Trial running started Kattappana Project Dn EE
07 Jul 2021 All the packages under this work are completed Kattappana Project Dn EE
01 Jun 2021 Electric Connection to be obtained for commissioning the scheme Kattappana Project Dn EE
14 May 2021 OHSR complete.Pump house completed.Pump set erected.Pressure filter connection works in progress.Application for electric connection submitted Kattappana Project Dn EE
18 Mar 2021 OHSR Structure completed.Interconnection works in progress Kattappana Project Dn EE
25 Jan 2021 OHSR Columns up to Base Slab Completed Kattappana Project Dn EE
23 Dec 2020 Laying of Pumping Main (1500m) Completed. Laying of Distribution 1000m out of 1800m Completed. OHSR First Brace Completed. Tender for Raw Water Pumps invited. Kattappana Project Dn EE
18 Dec 2020 Over all 75% Completed Kattappana Project Dn EE
23 Nov 2020 Laying of pumping and distribution mains started Kattappana Project Dn EE