Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 May 2024 | Design and drawings submitted to circle for approval | Kochi WS Dn EE | |
27 Apr 2024 | Site handed over | Thrikkakara Section AE | |
22 Apr 2024 | Site handed over | Thrikkakara Section AE | |
17 Apr 2024 | Site handed over | Thrikkakara Section AE | |
26 Mar 2024 | Agreement executed | Thrikkakara Section AE | |
20 Mar 2024 | Agreement executed | Thrikkakara Section AE | |
04 Mar 2024 | LoA issued on 24.01.2024 | Kochi WS Dn EE | |
15 Feb 2024 | Tender under scrutiny | Thrikkakara Section AE | |
17 Jan 2024 | Tender under scrutiny | Kochi WS Dn EE | |
05 Jan 2024 | Tender under scrutiny | Kochi WS Dn EE |