| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Jun 2022 | completed | Payyannur WS Sn - AE | |
| 10 Jun 2022 | PIPE SUPPLIED ....LAYING ONGOING | Payyannur WS Sn - AE | |
| 02 Jun 2022 | PIPE SUPPLIED ....LAYING ONGOING | Payyannur WS Sn - AE | |
| 30 May 2022 | PIPE SUPPLIED ....LAYING ONGOING | Payyannur WS Sn - AE | |
| 27 May 2022 | PIPE SUPPLIED ....LAYING ONGOING | Payyannur WS Sn - AE | |
| 25 May 2022 | PIPE SUPPLIED ....LAYING ONGOING | Payyannur WS Sn - AE | |
| 21 May 2022 | PIPE SUPPLIED ....LAYING ONGOING | Payyannur WS Sn - AE | |
| 18 May 2022 | PIPE SUPPLIED ....LAYING ONGOING | Payyannur WS Sn - AE | |
| 16 May 2022 | PIPE SUPPLIED ....LAYING ONGOING | Payyannur WS Sn - AE | |
| 13 May 2022 | PIPE SUPPLIED ....LAYING ONGOING | Payyannur WS Sn - AE |