| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Mar 2023 | Work completed and bill submitted to Division office. | Kannur WS Sub-Dn - AEE | |
| 22 Oct 2022 | Work completed bill under preparation | Kannur PH Sn 3 AE | |
| 14 Oct 2022 | work completed | Kannur PH Sn 3 AE | |
| 10 Oct 2022 | work completed | Kannur PH Sn 3 AE | |
| 06 Oct 2022 | Work completed | Kannur PH Sn 3 AE | |
| 30 Sep 2022 | Work completed | Kannur PH Sn 3 AE | |
| 26 Sep 2022 | Not started | Kannur PH Sn 3 AE | |
| 20 Sep 2022 | Not started | Kannur PH Sn 3 AE | |
| 16 Sep 2022 | work not started | Kannur PH Sn 3 AE |