Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Mar 2021 | Bill Settled | Kochi QC Dn EE | |
26 Feb 2021 | Bill submission delayed as vendor bank approval in PFMS was done only on 26.02.2021. Bill being submitted | Kochi QC Dn EE | |
13 Feb 2021 | bill submitted to Dn on 11.02.2021 | Kochi QC Dn EE | |
10 Feb 2021 | completed Bill at sub Dn | Kochi QC Dn EE | |
27 Jan 2021 | work completed on 23rd january | Kochi QC Dn EE | |
01 Dec 2020 | Roof concreting of bacteriology lab completed on 28-11-2020 | Kochi QC Dn EE |