| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Sep 2021 | 3067 FHTC GIVEN &25 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 01 Sep 2021 | 2928 FHTC GIVEN &25 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 24 Aug 2021 | 2928 FHTC GIVEN &25 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 17 Aug 2021 | 2770 FHTC GIVEN &25 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 10 Aug 2021 | 2770 FHTC GIVEN &25 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 06 Aug 2021 | 2770 FHTC GIVEN &25 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 02 Aug 2021 | 2670 FHTC GIVEN &25 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 26 Jul 2021 | 2670 FHTC GIVEN &25 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 20 Jul 2021 | 2588 FHTC GIVEN & 25 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 15 Jul 2021 | 2588 FHTC GIVEN & 25 KM PIPE LINE LAID | Thalassery PH Sn AE |