| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Aug 2024 | Work started. roofing works are going on. | Keezhallur PH Sn AE | |
| 05 Aug 2024 | Work started. roofing works are going on. | Keezhallur PH Sn AE | |
| 24 Jul 2024 | package V- work started. roofing works are going on. | Keezhallur PH Sn AE | |
| 13 Jul 2022 | Work completed & Final bill submited | Thalassery PH Sn AE | |
| 06 May 2022 | 3720 FHTC GIVEN & 28.3 KM PIPE LINE COMPLETED | Thalassery PH Sn AE | |
| 19 Apr 2022 | 3720 FHTC GIVEN &27 KM PIPE LINE COMPLETED | Thalassery PH Sn AE | |
| 10 Mar 2022 | 3579 FHTC GIVEN &27 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 02 Mar 2022 | 3579 FHTC GIVEN &27 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 03 Feb 2022 | 3579 FHTC GIVEN &27 KM PIPE LINE LAID | Thalassery PH Sn AE | |
| 29 Jan 2022 | 3537 FHTC GIVEN &27 KM PIPE LINE LAID | Thalassery PH Sn AE |