Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 Aug 2023 | Bill submitted to subdivision on 17.08.2023 | Vytilla Section AE - 2 | |
01 Aug 2023 | Work completed.Bill under preparation | Vytilla Section AE - 2 | |
14 Jul 2023 | Work completed.Bill under preparation | Vytilla Section AE - 2 | |
05 Jul 2023 | Work completed.Bill under preparation | Vytilla Section AE - 2 | |
27 Jun 2023 | Work completed.Bill under preparation | Vytilla Section AE - 2 | |
19 Jun 2023 | Work completed.Bill under preparation | Vytilla Section AE - 2 | |
16 Jun 2023 | Work completed.Bill under preparation | Vytilla Section AE - 2 | |
08 Jun 2023 | Bill under preparation | Vytilla Section AE - 2 | |
05 Jun 2023 | Work completed | Vytilla Section AE - 2 | |
01 Jun 2023 | road restoration work ongoing after pipe laying completion . | Kochi PH Dn EE |