Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 May 2024 | Out of 7500 FHTCs, around 71 HTC's done and 804 FHTC's. out of 110 mm PVC laid 33500 meter PVC pipe to be laid 16140 meter laying has been completed. | Alappuzha Project Dn PM | |
08 May 2024 | Out of 7500 FHTCs, around 67 HTC's done and 800 FHTC's. out of 110 mm PVC laid 33500 meter PVC pipe to be laid 15542.65 meter laying has been completed. | Alappuzha Project Dn PM | |
23 Apr 2024 | Out of 7500 FHTCs, around 299 HTC's done and 443 FHTC's. out of 110 mm PVC laid 33500 meter PVC pipe to be laid 13196meter laying has been completed. | Alappuzha Project Dn PM | |
19 Apr 2024 | Out of 7500 FHTCs, around 299 HTC's done and 443 FHTC's. out of 110 mm PVC laid 33500 meter PVC pipe to be laid 13196meter laying has been completed. | Alappuzha Project Dn PM | |
16 Apr 2024 | 110 mm PVC laid out of 33500 meter PVC pipe to be laid 12680 meter laying has been completed, Out of 7500 FHTCs, around 251 HTC's done and 415 FHTC's . | Alappuzha Project Dn PM | |
11 Apr 2024 | 110 mm PVC laid out of 33500 meter PVC pipe to be laid 12186.5 meter laying has been completed, Out of 7500 FHTCs, around 226 HTC's done and 336 FHTC's . | Alappuzha Project Dn PM | |
06 Apr 2024 | 110 mm PVC laid out of 33500 meter PVC pipe to be laid 2186.5 meter laying has been completed, Out of 7500 FHTCs, around 230 HTC's done and 264 FHTC's . | Alappuzha Project Dn PM | |
20 Mar 2024 | 110 mm PVC laid out of 33500 meter PVC pipe to be laid 11682.6 meter laying has been completed, Out of 7500 FHTCs, around 262 HTCs done. | Alappuzha Project Dn PM | |
21 Feb 2024 | Alappuzha municipality Laying 110 mm PVC laid out of 33500-meter PVC pipe to be laid 8102.1-meter laying has been completed, 20 mm HDPE PE pipes supplied. Laying of pipes started at site . As per the direction of ward councilor , Connection work is progressing | Alappuzha Project Dn PM | |
12 Feb 2024 | Alappuzha municipality Laying 110 mm PVC laid out of 33500-meter PVC pipe to be laid 8102.1-meter laying has been completed, FHTC works has been Water meters have been installed, geo tagging not started. | Alappuzha Project Dn PM |