| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Feb 2025 | Trail run in progress | Thaliparamba WS Dn EE | |
| 14 Feb 2025 | Trail run in progress | Thaliparamba WS Dn EE | |
| 10 Feb 2025 | Trail run in progress | Thaliparamba WS Dn EE | |
| 07 Feb 2025 | Trail run in progress | Thaliparamba WS Dn EE | |
| 31 Jan 2025 | Trail run in progress | Thaliparamba WS Dn EE | |
| 28 Jan 2025 | Trail run in progress | Thaliparamba WS Dn EE | |
| 24 Jan 2025 | Trail run in progress | Thaliparamba WS Dn EE | |
| 13 Jan 2025 | work order issued on 15.10.2024 | Thaliparamba WS Dn EE | |
| 09 Jan 2025 | work order issued on 15.10.2024 | Thaliparamba WS Dn EE | |
| 06 Jan 2025 | work order issued on 15.10.2024 | Thaliparamba WS Dn EE |