Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Apr 2025 | work completed on 22/03/2025 | Payyannur WS Sn - AE | |
01 Apr 2025 | trail run completed | Thaliparamba WS Dn EE | |
28 Mar 2025 | trail run completed | Thaliparamba WS Dn EE | |
24 Mar 2025 | trail run completed | Thaliparamba WS Dn EE | |
21 Mar 2025 | trail run completed | Thaliparamba WS Dn EE | |
17 Mar 2025 | trail run completed | Thaliparamba WS Dn EE | |
11 Mar 2025 | trail run completed | Thaliparamba WS Dn EE | |
05 Mar 2025 | trail run completed | Thaliparamba WS Dn EE | |
27 Feb 2025 | trail run completed | Thaliparamba WS Dn EE | |
24 Feb 2025 | trail run completed | Thaliparamba WS Dn EE |