| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Sep 2024 | Completed | Manjeri AE | |
| 18 Feb 2022 | Demand note from KSEBreceived | Manjeri AE | |
| 16 Feb 2022 | consent for land of transformer for electrification of pump house ongoing | Manjeri AE | |
| 24 Jan 2022 | consent for land of transformer for electrification of pump house ongoing | Manjeri AE | |
| 01 Jan 2022 | consent for land of transformer for electrification of pump house ongoing | Manjeri AE | |
| 03 Dec 2021 | consent for land of transformer for electrification of pump house ongoing | Malappuram PH Dn EE | |
| 23 Nov 2021 | Bill submitted for 188 FHtcs. Procdures for getting consent for land of tranformer for electrification of pump house ongoing | Manjeri AE | |
| 08 Nov 2021 | Bill submitted for 188 FHtcs. Procdures for getting consent for land of tranformer for electrification of pump house ongoing. | Manjeri AE | |
| 02 Nov 2021 | process to obtain consent for land of transformer is on progress | Manjeri AE | |
| 20 Oct 2021 | Site visited along with KSEB for electrification. need consent from land owner for erecting transformer above MFL | Manjeri AE |