Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Sep 2024 Completed Manjeri AE
18 Feb 2022 Demand note from KSEBreceived Manjeri AE
16 Feb 2022 consent for land of transformer for electrification of pump house ongoing Manjeri AE
24 Jan 2022 consent for land of transformer for electrification of pump house ongoing Manjeri AE
01 Jan 2022 consent for land of transformer for electrification of pump house ongoing Manjeri AE
03 Dec 2021 consent for land of transformer for electrification of pump house ongoing Malappuram PH Dn EE
23 Nov 2021 Bill submitted for 188 FHtcs. Procdures for getting consent for land of tranformer for electrification of pump house ongoing Manjeri AE
08 Nov 2021 Bill submitted for 188 FHtcs. Procdures for getting consent for land of tranformer for electrification of pump house ongoing. Manjeri AE
02 Nov 2021 process to obtain consent for land of transformer is on progress Manjeri AE
20 Oct 2021 Site visited along with KSEB for electrification. need consent from land owner for erecting transformer above MFL Manjeri AE