| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Feb 2022 | Tender extended due to no participants, Due date on 15.02.2022 | Malappuram PH Dn EE | |
| 01 Feb 2022 | Work tendered due date on 01.02.2022 | Malappuram PH Dn EE | |
| 01 Feb 2022 | Work tendered, no offers received. | Malappuram PH Dn EE | |
| 01 Dec 2021 | Estimate submitted to SE for approval | Malappuram PH Dn EE | |
| 04 Nov 2021 | Waiting for PRICErate approval | Malappuram PH Dn EE | |
| 19 Oct 2021 | Waiting for PRICErate approval | Malappuram PH Dn EE | |
| 03 Oct 2021 | Waiting for approval of revised rate for pipes | Malappuram PH Dn EE | |
| 26 Sep 2021 | TS to be issued. waiting for confirmation of rate revision | Malappuram PH Dn EE | |
| 13 Sep 2021 | TS to be issued. waiting for confirmation of rate revision | Malappuram PH Dn EE | |
| 06 Sep 2021 | Revised estimate submitted | Manjeri AE |