Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 May 2025 2025 All Pipes supplied 90mm PVC 1900m laid All GI laying completed except 150mm (500m remaining Manjeri AE
26 May 2025 All Pipes supplied 90mm PVC 1900m laid All GI laying completed except 150mm (500m remaining), 80mm (450m remaining) Manjeri AE
22 May 2025 All Pipes supplied 90mm PVC 1900m laid All GI laying completed except 150mm (500m remaining), 80mm (450m remaining) Manjeri AE
19 May 2025 All Pipes supplied 90mm PVC 1900m laid All GI laying completed except 150mm (500m remaining), 80mm (450m remaining) Manjeri AE
12 May 2025 All Pipes supplied 90mm PVC 1900m laid All GI laying completed except 150mm (500m remaining), 80mm (450m remaining) Manjeri AE
05 May 2025 All Pipes supplied 90mm PVC 1900m laid All GI laying completed except 150mm (500m remaining), 80mm (450m remaining) Manjeri AE
28 Apr 2025 All Pipes supplied 90mm PVC 1900m laid All GI laying completed except 150mm (500m remaining), 80mm (450m remaining) Manjeri AE
01 Apr 2025 All Pipes supplied 90mm PVC 1900m laid All GI laying completed except 150mm (500m remaining), 80mm (450m remaining) Manjeri AE
28 Mar 2025 All Pipes supplied 90mm PVC 1900m laid All GI laying completed except 150mm (500m remaining), 80mm (450m remaining) Manjeri AE
25 Mar 2025 All Pipes supplied 90mm PVC 1900m laid All GI laying completed except 150mm (500m remaining), 80mm (450m remaining) Manjeri AE