Status Date Overall Project Status Project Officer Contact
12 Jun 2023 work completed. Kollam WS Sn 2 - AE
09 Jun 2023 bill under preparation. Kollam WS Sn 2 - AE
06 Jun 2023 Work started on 6/6/2023 and completed Kollam WS Sn 2 - AE
05 Jun 2023 Site handed over and work will start tomorrow. Kollam WS Sn 2 - AE
01 Jun 2023 Tested pipe not received Kollam WS Sn 2 - AE
29 May 2023 Tested pipe not received Kollam WS Sn 2 - AE
24 May 2023 Tested pipe not received Kollam WS Sn 2 - AE
22 May 2023 Tested pipe not received Kollam WS Sn 2 - AE
19 May 2023 Waiting for tested pipe Kollam WS Sn 2 - AE
15 May 2023 Waiting for tested pipe Kollam WS Sn 2 - AE