Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Apr 2022 | Bill Submitted | Chavasseryparamba WS Sn AE | |
08 Apr 2022 | Capacitor supplied by the contractor Installation work completed.Bill under preparation | Chavasseryparamba WS Sn AE | |
05 Apr 2022 | Capacitor supplied by the contractor Installation work completed.Bill under preparation | Chavasseryparamba WS Sn AE | |
30 Mar 2022 | Capacitor supplied by the contractor Installation work completed. | Chavasseryparamba WS Sn AE | |
24 Mar 2022 | Capacitor supplied by the contractor Installation work completed. | Chavasseryparamba WS Sn AE | |
19 Mar 2022 | Capacitor supplied by the contractor Installation work completed | Chavasseryparamba WS Sn AE | |
15 Mar 2022 | work order issued. Capacitor supplied by the contractor | Chavasseryparamba WS Sn AE | |
11 Mar 2022 | work order issued. Capacitor supplied by the contractor | Chavasseryparamba WS Sn AE | |
07 Mar 2022 | work order issued materials supplied | Chavasseryparamba WS Sn AE | |
03 Mar 2022 | work order issued materials supplied | Chavasseryparamba WS Sn AE |