Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Feb 2024 | Pipe line work progressing-6100 mtr completed, HTC work also in progress 250 numbers completed | Malappuram Project Dn EE | |
31 Jan 2024 | pipe line work progressing-6100 mtr completed, HTC work also in progress 250 numbers completed. | Malappuram Project Dn EE | |
30 Nov 2023 | pipe line work progressing-6000 mtr completed, HTC work also in progress 200 numbers completed. | Malappuram Project Dn EE | |
30 Sep 2023 | pipe line work progressing-5500 mtr completed, HTC work also in progress 200 numbers completed. | Malappuram Project Dn EE | |
30 Aug 2023 | pipe line work progressing-5000mtr completed, HTC work also in progress 200 numbers completed. | Malappuram Project Dn EE | |
30 Aug 2023 | pipe line work progressing-7000 mtr completed, HTC work also in progress 300 numbers completed. | Malappuram Project Dn EE | |
28 Jul 2023 | 4000 mtr pipe line compleated, 120 HTC Compleated | Malappuram Project Dn EE | |
19 Jun 2023 | 4000 mtr pipe line compleated, 120 HTC Compleated | Malappuram Project Dn | |
05 May 2023 | Pipe line work progressing-2000 mtr compleated,HTC work also in progress | Malappuram Project Dn | |
06 Mar 2023 | PIPE LINE WORK PROGRESSING | Malappuram Project Dn |