| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Jan 2023 | Final bill paid. Road reformation charges fund requested. | Thaliparamba WS Dn EE | |
| 18 Oct 2021 | Final bill submitted | Thaliparamba WS Dn EE | |
| 12 Oct 2021 | final bill under scrutiny | Thaliparamba WS Dn EE | |
| 29 Jun 2021 | final bill under preparation | Thaliparamba WS Dn EE | |
| 09 Apr 2021 | work completed. | Thaliparamba WS Dn EE | |
| 24 Feb 2021 | line charging in progress | Thaliparamba WS Dn EE | |
| 17 Feb 2021 | 99.5% completed | Thaliparamba WS Dn EE | |
| 03 Feb 2021 | 99% completed | Thaliparamba WS Dn EE | |
| 25 Jan 2021 | Overall project progress 99 % | Thaliparamba WS Dn EE | |
| 16 Dec 2020 | works arranged in 9 packages were completed and in additional 12 works 11 works completed and 1 work in progress. Which includes 3km distribution line. The work can be completed by january end. Overall project progress 98% completed. | Thaliparamba WS Dn EE |