19 Dec 2021 For replacement of distribution lines in Zone 3 and 4- Work Completed Alappuzha Project Dn AE 3
31 Oct 2021 For replacement of distribution lines in Zone 3 and 4- Work Completed Trial running of the new lines are progressing Alappuzha Project Dn AE4
27 Oct 2021 Arrangements for charging of Zone 4 is progressing Alappuzha Project Dn AE4
20 Oct 2021 The charging of lines in Zone 3 (Vadikadu Zone) completed Alappuzha Project Dn AE4
18 Oct 2021 No work due to elevated water level Alappuzha Project Dn AE4
16 Oct 2021 No work due to heavy rain Alappuzha Project Dn AE4
13 Oct 2021 124 km out of 126 Laid completely. Charging of lines progressing. Charging of lines temporarily stopped due to non avalability of enough water in the distribution system. This is due to low rate of pumping of Raw water for the scheme to 62 mld WTP Karumadi due to frequest leaks at Thakazhy-Kelamangalam reach of RWPM along Ambalapuzha Thiruvalla road. Action plan for charging has been submitted to SE for getting water from regular distribution. Charging schedule prepared and submitted to SE, EE PH Dn. AEE PH Dn AE PH Dn for getting water for charging and commissioning. Charging of Zone 3 Completed Alappuzha Project Dn AE4
13 Oct 2021 Construction Work Completed. Power connection and water connection works is in progress. Alappuzha Project Dn PM
11 Oct 2021 124 km out of 126 Laid completely. Charging of lines progressing. Charging of lines temporarily stopped due to non avalability of enough water in the distribution system. This is due to low rate of pumping of Raw water for the scheme to 62 mld WTP Karumadi due to frequest leaks at Thakazhy-Kelamangalam reach of RWPM along Ambalapuzha Thiruvalla road. Action plan for charging has been submitted to SE for getting water from regular distribution. Charging schedule prepared and submitted to SE, EE PH Dn. AEE PH Dn AE PH Dn for getting water for charging and commissioning. Alappuzha Project Dn AE4
06 Oct 2021 123 km out of 126 Laid completely. Charging of lines progressing. Charging of lines temporarily stopped due to non avalability of enough water in the distribution system. This is due to low rate of pumping of Raw water for the scheme to 62 mld WTP Karumadi due to frequest leaks at Thakazhy-Kelamangalam reach of RWPM along Ambalapuzha Thiruvalla road. Action plan for charging has been submitted to SE for getting water from regular distribution. Charging schedule prepared and submitted to SE, EE PH Dn. AEE PH Dn AE PH Dn for getting water for charging and commissioning. Alappuzha Project Dn AE4