Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Dec 2023 | work completed bill submitted to subdivision | Cherthala PH Section - AE | |
02 Aug 2023 | work in progress | Cherthala PH Section - AE | |
27 Jul 2023 | work in progress | Cherthala PH Section - AE | |
22 Jun 2023 | 83% | Cherthala PH Section - AE | |
21 Jun 2023 | 83% | Cherthala PH Section - AE | |
21 Jun 2023 | 90% | Cherthala PH Section - AE | |
20 Jun 2023 | WORK STARTED | Alappuzha PH Dn EE | |
12 Jun 2023 | 83% | Cherthala PH Section - AE | |
09 Jun 2023 | Agreement executed | Alappuzha PH Dn EE | |
09 Jun 2023 | Agreement executed | Alappuzha PH Dn EE |