Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Jun 2025 Work started, 85 % laying completed. Perlasserry Sn 1
27 May 2025 Work started, 80 % laying completed. Perlasserry Sn 1
16 May 2025 Work started, 75% laying completed. Perlasserry Sn 1
07 May 2025 Work started, 70% laying completed. Perlasserry Sn 1
29 Apr 2025 Work started, 48% laying completed. Perlasserry Sn 1
19 Apr 2025 Work started, 48% laying completed. Perlasserry Sn 1
15 Apr 2025 Work started, 48% laying completed. Perlasserry Sn 1
10 Apr 2025 Work started, 48% laying completed. Perlasserry Sn 1
01 Apr 2025 work started ,45% laying completed Perlasserry Sn 1
24 Mar 2025 Work started, 40% laying completed. Perlasserry Sn 1