Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Apr 2025 | Work started, 48% laying completed. | Perlasserry Sn 1 | |
10 Apr 2025 | Work started, 48% laying completed. | Perlasserry Sn 1 | |
01 Apr 2025 | work started ,45% laying completed | Perlasserry Sn 1 | |
24 Mar 2025 | Work started, 40% laying completed. | Perlasserry Sn 1 | |
17 Mar 2025 | Work started ,excavation 20% completed. | Perlasserry Sn 1 | |
27 Feb 2025 | LOA issued. PBG submitted for restoration fee ,road cutting permission pending. | Perlasserry Sn 1 | |
12 Feb 2025 | LOA issued. COP submitted ,road cutting permission pending. | Perlasserry Sn 1 | |
01 Feb 2025 | LOA issued. COP submitted ,road cutting permission pending. | Perlasserry Sn 1 | |
28 Jan 2025 | LOA issued. COP submitted ,road cutting permission pending. | Perlasserry Sn 1 | |
25 Jan 2025 | LOA issued. COP submitted ,road cutting permission pending. | Perlasserry Sn 1 |