Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Sep 2024 Package 1-95% Completed. Final Interconnection works are progressing. Package 2-70% Completed, ongoing Package 6-LOA Issued, Agreement not executed Package 3- recasted estimate submit for approval. Package -4,5,7,8,9-Retendered with due date (extended ) 30.08.2024. Package 4 -2 Offers received, Package5 -4 Offers received,Package7 -3 Offers received,Package8 -2 Offers received,Package9 -3 Offers received Alappuzha KIIFB - AEE 1
11 Sep 2024 Package 1-95% Completed. Final Interconnection works are progressing. Package 2-70% Completed, ongoing Package 6-LOA Issued, Agreement not executed Package 3- recasted estimate submit for approval. Package -4,5,7,8,9-Retendered with due date (extended ) 30.08.2024. Package 4 -2 Offers received, Package5 -4 Offers received,Package7 -3 Offers received,Package8 -2 Offers received,Package9 -3 Offers received Alappuzha KIIFB - AEE 1
10 Sep 2024 Package 1-95% Completed. Final Interconnection works are progressing. Package 2-70% Completed, ongoing Package 6-LOA Issued, Agreement not executed Package 3- recasted estimate submit for approval. Package -4,5,7,8,9-Retendered with due date (extended ) 30.08.2024. Package 4 -2 Offers received, Package5 -4 Offers received,Package7 -3 Offers received,Package8 -2 Offers received,Package9 -3 Offers received Alappuzha KIIFB - AEE 1
09 Sep 2024 Package 1-95% Completed. Final Interconnection works are progressing. Package 2-70% Completed, ongoing Package 6-LOA Issued, Agreement not executed Package 3- recasted estimate submit for approval. Package -4,5,7,8,9-Retendered with due date (extended ) 30.08.2024. Package 4 -2 Offers received, Package5 -4 Offers received,Package7 -3 Offers received,Package8 -2 Offers received,Package9 -3 Offers received Alappuzha KIIFB - AEE 1
08 Sep 2024 Package 1-95% Completed. Final Interconnection works are progressing. Package 2-70% Completed, ongoing Package 6-LOA Issued, Agreement not executed Package 3- recasted estimate submit for approval. Package -4,5,7,8,9-Retendered with due date (extended ) 30.08.2024. Package 4 -2 Offers received, Package5 -4 Offers received,Package7 -3 Offers received,Package8 -2 Offers received,Package9 -3 Offers received Alappuzha KIIFB - AEE 1
07 Sep 2024 Package 1-95% Completed. Final Interconnection works are progressing. Package 2-70% Completed, ongoing Package 6-LOA Issued, Agreement not executed Package 3- recasted estimate submit for approval. Package -4,5,7,8,9-Retendered with due date (extended ) 30.08.2024. Package 4 -2 Offers received, Package5 -4 Offers received,Package7 -3 Offers received,Package8 -2 Offers received,Package9 -3 Offers received Alappuzha KIIFB - AEE 1
06 Sep 2024 Package 1-95% Completed. Final Interconnection works are progressing. Package 2-70% Completed, ongoing Package 6-LOA Issued, Agreement not executed Package 3- recasted estimate submit for approval. Package -4,5,7,8,9-Retendered with due date (extended ) 30.08.2024. Package 4 -2 Offers received, Package5 -4 Offers received,Package7 -3 Offers received,Package8 -2 Offers received,Package9 -3 Offers received Alappuzha KIIFB - AEE 1
05 Sep 2024 Package 1-95% Completed. Final Interconnection works are progressing. Package 2-70% Completed, ongoing Package 6-LOA Issued, Agreement not executed Package 3- recasted estimate submit for approval. Package -4,5,7,8,9-Retendered with due date (extended ) 30.08.2024. Package 4 -2 Offers received, Package5 -4 Offers received,Package7 -3 Offers received,Package8 -2 Offers received,Package9 -3 Offers received Alappuzha KIIFB - AEE 1
04 Sep 2024 Package 1-95% Completed. Final Interconnection works are progressing. Package 2-70% Completed, ongoing Package 6-LOA Issued, Agreement not executed Package 3- recasted estimate submit for approval. Package -4,5,7,8,9-Retendered with due date (extended ) 30.08.2024. Package 4 -2 Offers received, Package5 -4 Offers received,Package7 -3 Offers received,Package8 -2 Offers received,Package9 -3 Offers received Alappuzha KIIFB - AEE 1
03 Sep 2024 Package 1-95% Completed. Final Interconnection works are progressing. Package 2-70% Completed, ongoing Package 6-LOA Issued, Agreement not executed Package 3- recasted estimate submit for approval. Package -4,5,7,8,9-Retendered with due date (extended ) 30.08.2024. Package 4 -2 Offers received, Package5 -4 Offers received,Package7 -3 Offers received,Package8 -2 Offers received,Package9 -3 Offers received Alappuzha KIIFB - AEE 1