| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 May 2021 | package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, sump side wall completed, clarifier and foculator footing completed, package 2- soil investigation for OHSR is completed, the design of OHSR is under preparation, package 2A- the soil investigation of OHSR site is completed and the design of ohsr is under progress ,package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign | Malappuram Project Dn AE6 | |
| 23 Apr 2021 | package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, sump side wall completed, clarifier and foculator footing completed, package 2- soil investigation for OHSR is completed, the design of OHSR is under preparation, package 2A- the soil investigation of OHSR site is completed and the design of ohsr is under progress ,package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign | Malappuram Project Dn AE6 | |
| 21 Apr 2021 | package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, sump side wall completed, clarifier and foculator footing completed, package 2- soil investigation for OHSR is completed, the design of OHSR is under preparation, package 2A- the soil investigation of OHSR site is completed and the design of ohsr is under progress ,package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign | Malappuram Project Dn AE6 | |
| 20 Apr 2021 | package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, sump side wall completed, clarifier and foculator footing completed, package 2- soil investigation for OHSR is completed, the design of OHSR is under preparation, package 2A- the soil investigation of OHSR site is completed and the design of ohsr is under progress ,package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign | Malappuram Project Dn AE6 | |
| 19 Apr 2021 | package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, sump side wall completed, clarifier and foculator footing completed, package 2- soil investigation for OHSR is completed, the design of OHSR is under preparation, package 2A- the soil investigation of OHSR site is completed and the design of ohsr is under progress ,package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign | Malappuram Project Dn AE6 | |
| 15 Apr 2021 | package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, sump side wall completed, clarifier and foculator footing completed, package 2- soil investigation for OHSR is completed, the design of OHSR is under preparation, package 2A- the soil investigation of OHSR site is completed and the design of ohsr is under progress ,package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign | Malappuram Project Dn AE6 | |
| 12 Apr 2021 | package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is in finishing stage, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign | Malappuram Project Dn AE6 | |
| 31 Mar 2021 | package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is in finishing stage, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign. as per the direction of district collector work temprorily stoped from 31/3/2021 to 7/4/2021 due to election | Malappuram Project Dn AE6 | |
| 29 Mar 2021 | package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is in finishing stage, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign | Malappuram Project Dn AE6 | |
| 24 Mar 2021 | package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, earth work excavation for WTP is in finishing stage, package 2- soil investigation for OHSR is conducted, the design of OHSR is under preparation, package 2A- the work order issued. the agrement not executed, the package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign | Malappuram Project Dn AE6 |