Status Date Overall Project Status Project Officer Contact
18 Nov 2021 pipe laying work in progress overall 50 percentage of work completed Malappuram Project Dn AE6
25 Sep 2021 package 1- 600mm DI K9 pipe 1306 meter supplied, 19 MLD WTP work 60 percent is completed,package 2- soil investigation for OHSR is completed, the design of OHSR is completed chammalaparamba ohsr work started , footing work in progress,80 pecentage of the pvc pipe is supplied package 2A- the soil investigation of OHSR site is completed and the design is completed and approved the footing work of the ohsr is n progress, ,package 3A-all PVC and GI pipe supplied- distribution network in zone 1 and 2 is completed zone 3 20 percentage is completed. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- tender approved, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
26 Aug 2021 package 1- 600mm DI K9 pipe 1306 meter supplied, 19 MLD WTP work 60 percent is completed,package 2- soil investigation for OHSR is completed, the design of OHSR is completed chammalaparamba ohsr work started , footing work in progress,80 pecentage of the pvc pipe is supplied package 2A- the soil investigation of OHSR site is completed and the design is completed and approved the footing work of the ohsr is n progress, ,package 3A-all PVC and GI pipe supplied- distribution network in zone 1 and 2 is completed zone 3 20 percentage is completed. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- tender approved, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
25 Aug 2021 package 1- 600mm DI K9 pipe 1306 meter supplied, 19 MLD WTP work 60 percent is completed,package 2- soil investigation for OHSR is completed, the design of OHSR is completed chammalaparamba ohsr work started , footing work in progress,80 pecentage of the pvc pipe is supplied package 2A- the soil investigation of OHSR site is completed and the design is completed and approved the footing work of the ohsr is n progress, ,package 3A-all PVC and GI pipe supplied- distribution network in zone 1 and 2 is completed zone 3 20 percentage is completed. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- tender approved, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
13 Jun 2021 package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, 8.3 LL capacity sump completed, clarifier and foculator footing and side wall up to 2 meter is completed,package 2- soil investigation for OHSR is completed, the design of OHSR is completed and send for vetting to GEC trissur, package 2A- the soil investigation of OHSR site is completed and the design is completed and approved, the site leveling in ogress ,package 3A-all PVC and GI pipe supplied- 68 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- tender approved, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
07 Jun 2021 package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, 8.3 LL capacity sump completed, clarifier and foculator footing and side wall up to 2 meter is completed,package 2- soil investigation for OHSR is completed, the design of OHSR is completed and send for vetting to GEC trissur, package 2A- the soil investigation of OHSR site is completed and the design is completed and approved, the site leveling in ogress ,package 3A-all PVC and GI pipe supplied- 68 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- tender approved, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
01 Jun 2021 package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, 8.3 LL capacity sump completed, clarifier and foculator footing and side wall up to 2 meter is completed,package 2- soil investigation for OHSR is completed, the design of OHSR is completed and send for vetting to GEC trissur, package 2A- the soil investigation of OHSR site is completed and the design is completed and approved, the site leveling in ogress ,package 3A-all PVC and GI pipe supplied- 68 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- tender approved, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
31 May 2021 package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, 8.3 LL capacity sump completed, clarifier and foculator footing completed, sidewall first stage in progress,package 2- soil investigation for OHSR is completed, the design of OHSR is under preparation, package 2A- the soil investigation of OHSR site is completed and the design of ohsr is under progress ,package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
12 May 2021 package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, 8.3 LL capacity sump completed, clarifier and foculator footing completed, sidewall first stage in progress,package 2- soil investigation for OHSR is completed, the design of OHSR is under preparation, package 2A- the soil investigation of OHSR site is completed and the design of ohsr is under progress ,package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6
07 May 2021 package 1- 600mm DI K9 pipe 1306 meter supplied, deisign of 19 MLD WTP is approved, sump side wall completed, clarifier and foculator footing completed, package 2- soil investigation for OHSR is completed, the design of OHSR is under preparation, package 2A- the soil investigation of OHSR site is completed and the design of ohsr is under progress ,package 3A-all PVC and GI pipe supplied- 62 Km of distribution pipe laid. the 200 mm DI pipe and 300 mm DI pipe supplied and started pipe supply , the road restoration in PWD roads 40 % completed, package 3B- TS obtainedl, Package 3c- estimate under preparation after redesign Malappuram Project Dn AE6