Package: AMRUT 2.0 -Block N-Laying Transmission main and sewer network in Block N(Uloor) - Ist reach-Sewerage Work
18/01/2025 by Thiruvananthapuram Project AE9 - 8547638417
On going | 5.00% Completed
Work order issued 16/03/2024.Pipe supplied on 06/08/2024. 630 mm HDPE Pipe 408 m and 710 mm HDPE Pipe 357 m arrived. work not started.
Package: AMRUT 2.0 -Block N-Providing Sewer lines for branch sewers to the collection mains of Block N -Providing branch sewers in Nithyasahaya matha church lane-Sewerage Work
18/01/2025 by Thiruvananthapuram Project AE9 - 8547638417
On going | 84.00% Completed
Work order issued on12/06/2024. 24/08/2024 200mm SW Pipe arrived. 200mm SW pipe 281m laid out of 312m.13 Manhole work fully completed. road restoration work progressing.
Package: AMRUT 2.0 -Block N-Providing Sewer lines for branch sewers to the collection mains of Block N -Providing branch sewers in Parottukonam - 2nd reach-Sewerage Work
18/01/2025 by Thiruvananthapuram Project AE9 - 8547638417
On going | 31.00% Completed
Work order issued on 04/08/2023. SW pipes were arrived on 04/10/2023. Manhole cover slab construction completed ( 13 Nos casted).110 mm PVC Pipe 150 m laid. 300 mm SW Pipe 60 m laid out of 318 m. 2 manhole work completed. Pipe laying work progressing.
Package: AMRUT-AMRUT 2.0 -Block N-Providing Sewer lines for branch sewers to the collection mains of Block N -Providing branch sewers in Chenthi Lane-Sewerage Work
18/01/2025 by Thiruvananthapuram Project AE9 - 8547638417
On going | 5.00% Completed
Work order issued on 09/01/2024.Pipe supplied on 08/08/2024.Work not started.
Package: AMRUT-AMRUT 2.0 - Block N-Providing Sewer lines for branch sewers to the collection mains of Block N -Providing branch sewers in E.K Nayanar road-Sewerage Work
18/01/2025 by Thiruvananthapuram Project AE9 - 8547638417
On going | 99.00% Completed
Work order issued on 04/08/2023.Pipe supplied on 29/09/2023. Manhole work and pipe laying work completed .Road restoration work completed.Final bill under preparation.
Package: AMRUT-AMRUT 2.0 -Block N-Providing Sewer lines for branch sewers to the collection mains of Block N -Providing branch sewers in Mosque Lane-Sewerage Work
18/01/2025 by Thiruvananthapuram Project AE9 - 8547638417
On going | 32.00% Completed
Work order issued on 05/01/2024. 300mm SW pipe 0m laid out of 88.5m & 220mm SW pipe 200m laid out of 686m. 8manhole work fully completed.5 Cover slab work completed. 6manhole work partually completted. Manhole work progressing.
Package: AMRUT-AMRUT 2.0 -Block N-Providing Sewer lines for branch sewers to the collection mains of Block N -Providing branch sewers in Thoppil Lane and Chathanpara Lane-Sewerage Work
18/01/2025 by Thiruvananthapuram Project AE9 - 8547638417
On going | 96.00% Completed
All work complete except house connection work.
Package: AMRUT-AMRUT 2.0 -Block N-TSS BLOCK NConstruction of sewer Pumping station at Kollavila in Block N Ulloor-Sewerage Work
18/01/2025 by Thiruvananthapuram Project AE9 - 8547638417
On going | 51.00% Completed
Grit chamber Work Completed. Well steining 6th lift Completed .Lateral Manhole Steining 5th lift Completed . Well Rock Blasting and bailing out work progressing.