Progress Information of - Jal Jeevan Mission (JJM)-JJM - WSS to Aloor and Kodakara (Part I) Panchayaths in Thrissur District

Package: JJM - WSS to Aloor and Kodakara (Part I) Panchayaths in Thrissur District-Construction of 12 LL OHSR at Porunankunnu & Valve chamber-Structural Design Work-1

16/01/2025 by Nattika AE 3 - 9400002036

On going | 83.00% Completed

Site clearance ,site set out and building set out completed. Excavation for tank foundation completed. PCC for footing -30 Nos. completed. Footing concrete-30 Nos. completed. Column pedastal concreting completed. PCC Concreting of footing ( 12 Nos.) completed. Reinforcement work for footing completed. Concreting of footing (12 Nos.) completed. Reinforcement and shuttering work for column pedestal completed. Concreting for column pedestal completed. Back filling completed. Reinforcement work and shuttering work for plinth beam completed. Plinth beam concreting completed. Reinforcement work and shuttering work for First level columns completed. First level outer column (22 Nos ) concreting completed. Reinforcement work and shuttering work for stair (First flight) completed. Reinforcement work and shuttering work for inner columns (18 Nos ) completed. Concreting of column-18 Nos (1.35 height) ,Ground floor stair (First flight) completed. Re shuttering of column (18 nos) completed. Column centering and reinforcement work completed. Reinforcement work for 20 columns completed. First brace beam centering and reinforcement work completed. Concreting of first brace beam and second flight stair completed. Reinforcement work for second level column and shuttering work completed. Concreting of third flight stair and landing slab completed. Second level column concreting completed. Shuttering work and reinforcement work for second brace beam completed. Concreting of second brace beam completed. Reinforcement and shuttering work of third brace column completed. Concreting of fourth flight stair and landing slab completed. Concreting of third brace column completed. Concreting of third brace beam completed. Reinforcement work and shuttering work of slab completed. Concreting of floor slab completed. Concreting of fifth flight of stair completed. Shuttering and reinforcement work for column (above floor slab) completed. Side wall concreting (440 cm) completed. Concreting of column (above floor slab) completed. Concreting of partition wall completed. Reinforcement and shuttering work for roof slab completed. Concreting of roof slab completed. Concreting of stair completed. Plastering work and painting work ongoing.

15/01/2025 by Nattika AE 3 - 9400002036

On going | 83.00% Completed

Site clearance ,site set out and building set out completed. Excavation for tank foundation completed. PCC for footing -30 Nos. completed. Footing concrete-30 Nos. completed. Column pedastal concreting completed. PCC Concreting of footing ( 12 Nos.) completed. Reinforcement work for footing completed. Concreting of footing (12 Nos.) completed. Reinforcement and shuttering work for column pedestal completed. Concreting for column pedestal completed. Back filling completed. Reinforcement work and shuttering work for plinth beam completed. Plinth beam concreting completed. Reinforcement work and shuttering work for First level columns completed. First level outer column (22 Nos ) concreting completed. Reinforcement work and shuttering work for stair (First flight) completed. Reinforcement work and shuttering work for inner columns (18 Nos ) completed. Concreting of column-18 Nos (1.35 height) ,Ground floor stair (First flight) completed. Re shuttering of column (18 nos) completed. Column centering and reinforcement work completed. Reinforcement work for 20 columns completed. First brace beam centering and reinforcement work completed. Concreting of first brace beam and second flight stair completed. Reinforcement work for second level column and shuttering work completed. Concreting of third flight stair and landing slab completed. Second level column concreting completed. Shuttering work and reinforcement work for second brace beam completed. Concreting of second brace beam completed. Reinforcement and shuttering work of third brace column completed. Concreting of fourth flight stair and landing slab completed. Concreting of third brace column completed. Concreting of third brace beam completed. Reinforcement work and shuttering work of slab completed. Concreting of floor slab completed. Concreting of fifth flight of stair completed. Shuttering and reinforcement work for column (above floor slab) completed. Side wall concreting (440 cm) completed. Concreting of column (above floor slab) completed. Concreting of partition wall completed. Reinforcement and shuttering work for roof slab completed. Concreting of roof slab completed. Concreting of stair completed. Plastering work and painting work ongoing.

14/01/2025 by Nattika AE 3 - 9400002036

On going | 83.00% Completed

Site clearance ,site set out and building set out completed. Excavation for tank foundation completed. PCC for footing -30 Nos. completed. Footing concrete-30 Nos. completed. Column pedastal concreting completed. PCC Concreting of footing ( 12 Nos.) completed. Reinforcement work for footing completed. Concreting of footing (12 Nos.) completed. Reinforcement and shuttering work for column pedestal completed. Concreting for column pedestal completed. Back filling completed. Reinforcement work and shuttering work for plinth beam completed. Plinth beam concreting completed. Reinforcement work and shuttering work for First level columns completed. First level outer column (22 Nos ) concreting completed. Reinforcement work and shuttering work for stair (First flight) completed. Reinforcement work and shuttering work for inner columns (18 Nos ) completed. Concreting of column-18 Nos (1.35 height) ,Ground floor stair (First flight) completed. Re shuttering of column (18 nos) completed. Column centering and reinforcement work completed. Reinforcement work for 20 columns completed. First brace beam centering and reinforcement work completed. Concreting of first brace beam and second flight stair completed. Reinforcement work for second level column and shuttering work completed. Concreting of third flight stair and landing slab completed. Second level column concreting completed. Shuttering work and reinforcement work for second brace beam completed. Concreting of second brace beam completed. Reinforcement and shuttering work of third brace column completed. Concreting of fourth flight stair and landing slab completed. Concreting of third brace column completed. Concreting of third brace beam completed. Reinforcement work and shuttering work of slab completed. Concreting of floor slab completed. Concreting of fifth flight of stair completed. Shuttering and reinforcement work for column (above floor slab) completed. Side wall concreting (440 cm) completed. Concreting of column (above floor slab) completed. Concreting of partition wall completed. Reinforcement and shuttering work for roof slab completed. Concreting of roof slab completed. Concreting of stair completed. Plastering work and painting work ongoing.