Progress Information of - PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)

Package: Supply,erection,commissioning and maintaining of Clear Water pump sets and Electrical Sub stations at TP site

07/10/2021 by Kollam Project HD - 8281597976

On going | 1.00% Completed

The estimate return by CE and directed to revise the estimate and re design the Raw water pump set incorporating the demand of 4 panchayath (Perinadu, Thrikkaruva,Panayam and Mandrothuruth). Also as per the existing rules of KWA if the Capacity of C F pump set is more than 200 HP it is necessary to provide H T connection. As per the new IS Code it is better to provide energy efficiency motors having LT connections. Hence clarification from higher authorities is required the same has been intimated to CE for getting sanction from Higher Authorities The estimate return by CE and directed to revise the estimate and re design the Raw water pump set incorporating the demand of 4 panchayath (Perinadu, Thrikkaruva,Panayam and Mandrothuruth). Also as per the existing rules of KWA if the Capacity of C F pump set is more than 200 HP it is necessary to provide H T connection. As per the new IS Code it is better to provide energy efficiency motors having LT connections. Hence clarification from higher authorities is required the same has been intimated to CE for getting sanction from Higher Authorities

Package: Supply,erection,commissioning and maintaining of Raw Water pump sets and Electrical Sub stations at Intake

07/10/2021 by Kollam Project HD - 8281597976

On going | 1.00% Completed

The estimate return by CE and directed to revise the estimate and re design the Raw water pump set incorporating the demand of 4 panchayath (Perinadu, Thrikkaruva,Panayam and Mandrothuruth). Also as per the existing rules of KWA if the Capacity of C F pump set is more than 200 HP it is necessary to provide H T connection. As per the new IS Code it is better to provide energy efficiency motors having LT connections. Hence clarification from higher authorities is required the same has been intimated to CE for getting sanction from Higher Authorities The estimate return by CE and directed to revise the estimate and re design the Raw water pump set incorporating the demand of 4 panchayath (Perinadu, Thrikkaruva,Panayam and Mandrothuruth). Also as per the existing rules of KWA if the Capacity of C F pump set is more than 200 HP it is necessary to provide H T connection. As per the new IS Code it is better to provide energy efficiency motors having LT connections. Hence clarification from higher authorities is required the same has been intimated to CE for getting sanction from Higher Authorities

Package: Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode

07/10/2021 by Kollam Project HD - 8281597976

On going | 38.00% Completed

914 mm dia MS pipe laying work in progress at Lekshminada - Thankassery road. 914mm Laying Total 2970.86m completed, 1016mm laying from 2 nd no jn to Manichithod - Total 414.75 m laying work completed.914 mm GM-In lining and Out coating works are in Progress. 466 Nos. of pipe In lining works and 453nos. of Out coating works are completed.1016 mm GM-In lining work in Progress. 308 Nos. of pipe In lining work and 308 nos. of out coating works are completed. 54 LL OHSR - Floor slab concrete work completed , Reinforcement work of tank side wall and inside column work in progress 914 mm dia MS pipe laying work in progress at Lekshminada - Thankassery road. 914mm Laying Total 2970.86m completed, 1016mm laying from 2 nd no jn to Manichithod - Total 414.75 m laying work completed.914 mm GM-In lining and Out coating works are in Progress. 466 Nos. of pipe In lining works and 453nos. of Out coating works are completed.1016 mm GM-In lining work in Progress. 308 Nos. of pipe In lining work and 308 nos. of out coating works are completed. 54 LL OHSR - Floor slab concrete work completed , Reinforcement work of tank side wall and inside column work in progress

04/10/2021 by Kollam Project HD - 8281597976

On going | 38.00% Completed

914 mm dia MS pipe laying work in progress at Lekshminada - Thankassery road. 914mm Laying Total 2958.86m completed, 1016mm laying from 2 nd no jn to Manichithod - Total 414.75 m laying work completed.914 mm GM-In lining and Out coating works are in Progress. 462 Nos. of pipe In lining works and 443nos. of Out coating works are completed.1016 mm GM-In lining work in Progress. 308 Nos. of pipe In lining work and 308 nos. of out coating works are completed. 54 LL OHSR - Floor slab concrete work completed , Reinforcement work of tank side wall and inside column work in progress 914 mm dia MS pipe laying work in progress at Lekshminada - Thankassery road. 914mm Laying Total 2958.86m completed, 1016mm laying from 2 nd no jn to Manichithod - Total 414.75 m laying work completed.914 mm GM-In lining and Out coating works are in Progress. 462 Nos. of pipe In lining works and 443nos. of Out coating works are completed.1016 mm GM-In lining work in Progress. 308 Nos. of pipe In lining work and 308 nos. of out coating works are completed. 54 LL OHSR - Floor slab concrete work completed , Reinforcement work of tank side wall and inside column work in progress

03/10/2021 by Kollam Project HD - 8281597976

On going | 38.00% Completed

914 mm dia MS pipe laying work in progress at Lekshminada - Thankassery road. 914mm Laying Total 2923.52m completed, 1016mm laying from 2 nd no jn to Manichithod - Total 414.75 m laying work completed.914 mm GM-In lining and Out coating works are in Progress. 462 Nos. of pipe In lining works and 437nos. of Out coating works are completed.1016 mm GM-In lining work in Progress. 308 Nos. of pipe In lining work and 308 nos. of out coating works are completed. 54 LL OHSR - Floor slab concrete work completed , Reinforcement work of tank side wall and inside column work in progress 914 mm dia MS pipe laying work in progress at Lekshminada - Thankassery road. 914mm Laying Total 2923.52m completed, 1016mm laying from 2 nd no jn to Manichithod - Total 414.75 m laying work completed.914 mm GM-In lining and Out coating works are in Progress. 462 Nos. of pipe In lining works and 437nos. of Out coating works are completed.1016 mm GM-In lining work in Progress. 308 Nos. of pipe In lining work and 308 nos. of out coating works are completed. 54 LL OHSR - Floor slab concrete work completed , Reinforcement work of tank side wall and inside column work in progress

Package: Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira

06/10/2021 by Kollam Project HD - 8281597976

On going | 96.00% Completed

Laying works are in progress at Nanthirikkal Panchayath road.Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work completed. 22 th hydrotest completed . Total HYDROTEST 26035.87 METER COMPLETED. Plastering work of Valve chambers work in progress 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed.Punthalathazhom scour valve chamber floor concrete work completed. Laying works are in progress at Nanthirikkal Panchayath road.Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work completed. 22 th hydrotest completed . Total HYDROTEST 26035.87 METER COMPLETED. Plastering work of Valve chambers work in progress 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed.Punthalathazhom scour valve chamber floor concrete work completed.

05/10/2021 by Kollam Project HD - 8281597976

On going | 96.00% Completed

Laying works are in progress at Nanthirikkal Panchayath road.Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work completed. 22 th hydrotest completed . Total HYDROTEST 26035.87 METER COMPLETED. Plastering work of Valve chambers work in progress 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed Laying works are in progress at Nanthirikkal Panchayath road.Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work completed. 22 th hydrotest completed . Total HYDROTEST 26035.87 METER COMPLETED. Plastering work of Valve chambers work in progress 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed