Go Back

Progress Information of - DISTRICT PT-DEPOSIT WORK-URBAN AGGLOMERATION-Kalady Pt.-Replacement of 300 mm Raw Water Pumping main by using 300 mm DI K9 Pipe and allied works

Package: DISTRICT PT-DEPOSIT WORK-URBAN AGGLOMERATION-Kalady Pt.-Replacement of 300 mm Raw Water Pumping main by using 300 mm DI K9 Pipe and allied works

16/09/2021 by Angamaly AEE - 8547638164

Non starter | 0.00% Completed

not started TS can be issued after approval of rates of pipe from Govt.

15/09/2021 by Angamaly AEE - 8547638164

Non starter | 0.00% Completed

0 % TS can be issued after approval of rates of pipe from Govt.

14/09/2021 by Angamaly AEE - 8547638164

Non starter | 0.00% Completed

0 % TS can be issued after approval of rates of pipe from Govt.

13/09/2021 by Angamaly AEE - 8547638164

Non starter | 0.00% Completed

not started. TS can be issued after approval of rates of pipe from Govt.