Go Back

Progress Information of - JJM-Providing retrofittable/extendable water service connections in Thrikkunnapuzha Panchayath in Alappuzha District-work 2

Package: JJM-Providing retrofittable/extendable water service connections in Thrikkunnapuzha Panchayath in Alappuzha District-work 2

09/09/2021 by Alappuzha Project Dn PM - 8547638100

On going | 86.00% Completed

69/75 FHTC COMPLETED. Pipe line laying work is pending due to want of Private property consent. Informed to Panchayath authorities 69/75 FHTC COMPLETED. Pipe line laying work is pending due to want of Private property consent. Informed to Panchayath authorities

07/09/2021 by Alappuzha Project Dn PM - 8547638100

On going | 86.00% Completed

69/75 FHTC COMPLETED. Pipe line laying work is pending due to want of Private property consent. Informed to Panchayath authorities 69/75 FHTC COMPLETED. Pipe line laying work is pending due to want of Private property consent. Informed to Panchayath authorities