Go Back

Progress Information of - Name of Work : Deposit work-District Panchayath. Extension of pipe lines at NH -66 Block office PHC road ,Near Panackal pally road , Krishibhavan Attiveli road , Valavanadu - PHC road , Manichandhayil - Mannamparambu road in Mannancherry Grama Panchayath.

Package: Deposit work-District Panchayath. Extension of pipe lines at NH -66 Block office PHC road ,Near Panackal pally road , Krishibhavan Attiveli road , Valavanadu - PHC road , Manichandhayil - Mannamparambu road in Mannancherry Grama Panchayath.

11/09/2021 by Cherthala PH SUb Dn - 8547638225

On going | 95.00% Completed

Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season

10/09/2021 by Cherthala PH SUb Dn - 8547638225

On going | 95.00% Completed

Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season

08/09/2021 by Cherthala PH SUb Dn - 8547638225

On going | 95.00% Completed

Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season

07/09/2021 by Cherthala PH SUb Dn - 8547638225

On going | 95.00% Completed

Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season

06/09/2021 by Cherthala PH SUb Dn - 8547638225

On going | 95.00% Completed

Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season

05/09/2021 by Cherthala PH SUb Dn - 8547638225

On going | 95.00% Completed

Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season Amount remitted to PWD and challan uploaded in ROW portal , awaiting sanction proceedings from PWD for interconnection. Expected to get the same after the rainy season