Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Perlasserry Sn 1
Date: 21/04/2026

Work has been completed | 100% Completed

Work completed

Perlasserry Sn 1
Date: 15/04/2026

Work in progress | 95% Completed

Work in progress.

Perlasserry Sn 1
Date: 10/04/2026

Work in progress | 95% Completed

Work in progress

Perlasserry Sn 1
Date: 05/04/2026

Work in progress | 90% Completed

Work in progress. 90% completed.

Perlasserry Sn 1
Date: 30/03/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 25/03/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 21/03/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 17/03/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 10/03/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 07/03/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 02/03/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 27/02/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 22/02/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 19/02/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 11/02/2026

Work in progress | 80% Completed

Work in progress. 80% completed.

Perlasserry Sn 1
Date: 04/02/2026

Work in progress | 78% Completed

Work in progress. 78% completed.

Perlasserry Sn 1
Date: 31/01/2026

Work in progress | 78% Completed

Work in progress. 78% completed.

Perlasserry Sn 1
Date: 21/01/2026

Work in progress | 78% Completed

Work in progress. 78% completed.

Perlasserry Sn 1
Date: 17/01/2026

Work in progress | 78% Completed

Work in progress. 78% completed.

Perlasserry Sn 1
Date: 13/01/2026

Work in progress | 75% Completed

Work in progress. 75% completed.

Perlasserry Sn 1
Date: 06/01/2026

Work in progress | 75% Completed

Work in progress. 75% completed.

Perlasserry Sn 1
Date: 01/01/2026

Work in progress | 75% Completed

Work in progress. 75% completed.

Perlasserry Sn 1
Date: 26/12/2025

Work in progress | 70% Completed

Work in progress. 70% completed.

Perlasserry Sn 1
Date: 22/12/2025

Work in progress | 70% Completed

Work in progress. 70% completed.

Perlasserry Sn 1
Date: 16/12/2025

Work in progress | 70% Completed

Work in progress. 70% completed.

Perlasserry Sn 1
Date: 09/12/2025

Work in progress | 70% Completed

Work in progress. 70% completed.

Perlasserry Sn 1
Date: 03/12/2025

Work in progress | 70% Completed

Work in progress. 70% completed.

Perlasserry Sn 1
Date: 26/11/2025

Work in progress | 70% Completed

Work in progress. 70% completed.

Perlasserry Sn 1
Date: 19/11/2025

Work in progress | 65% Completed

Work in progress. 65% completed.

Perlasserry Sn 1
Date: 13/11/2025

Work in progress | 65% Completed

Work in progress. 60% completed.

Perlasserry Sn 1
Date: 06/11/2025

Work in progress | 60% Completed

Work in progress. 60% completed.

Perlasserry Sn 1
Date: 01/11/2025

Work in progress | 60% Completed

Work in progress. 60% completed.

Perlasserry Sn 1
Date: 28/10/2025

Work in progress | 60% Completed

Work in progress. 60% completed.

Perlasserry Sn 1
Date: 22/10/2025

Work in progress | 50% Completed

The work has resumed. Out of 2500m pipe line proposed , 1500m pipe line laying has been completed.

Perlasserry Sn 1
Date: 16/10/2025

Work in progress | 40% Completed

40% COMPLETED

Perlasserry Sn 1
Date: 26/09/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 18/09/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 12/09/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 08/09/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 27/08/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 21/08/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 14/08/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 08/08/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 02/08/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 28/07/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 16/07/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 10/07/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 08/07/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 02/07/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 28/06/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 24/06/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 17/06/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 09/06/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 16/05/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 07/05/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 29/04/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 19/04/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 15/04/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 10/04/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 01/04/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 24/03/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 17/03/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 27/02/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.

Perlasserry Sn 1
Date: 12/02/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 01/02/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 28/01/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 25/01/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 18/01/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 13/01/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath. 2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 04/01/2025

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.

Perlasserry Sn 1
Date: 31/12/2024

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.

Perlasserry Sn 1
Date: 21/12/2024

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.

Perlasserry Sn 1
Date: 17/12/2024

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.

Perlasserry Sn 1
Date: 10/12/2024

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.

Perlasserry Sn 1
Date: 03/12/2024

Work in progress | 25% Completed

The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.

Perlasserry Sn 1
Date: 27/11/2024

Work in progress | 25% Completed

The work has been stopped temporarily due to the objection from the panchayath.2500 M pipe proposed - 700 M completed.

Perlasserry Sn 1
Date: 13/11/2024

Work in progress | 25% Completed

The work has been stopped temporarily due to the objection from the panchayath.2500 M pipe proposed - 700 M completed.

Perlasserry Sn 1
Date: 06/11/2024

Work in progress | 25% Completed

The work has been stopped due to the objection from the panchayath.

Perlasserry Sn 1
Date: 02/11/2024

Work in progress | 25% Completed

2500M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 28/10/2024

Work in progress | 25% Completed

2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 22/10/2024

Work in progress | 25% Completed

2500 M PIPE PROPOSED - 700 M COMPLETED

Perlasserry Sn 1
Date: 19/10/2024

Work in progress | 25% Completed

700 m of pipe laid.

Perlasserry Sn 1
Date: 15/10/2024

Work in progress | 10% Completed

WORK IN PROGRESS

Perlasserry Sn 1
Date: 10/10/2024

Work in progress | 10% Completed

300m pipe laid.

Kannur PH Dn EE
Date: 04/10/2024

Work has started | 0% Completed

Work order issued on 14-08-2024, agreement not executed.

Kannur PH Dn EE
Date: 24/09/2024

Work has started | 0% Completed

Work order issued on 14-08-2024, agreement not executed.

Perlasserry Sn 1
Date: 11/09/2024

Work has started | 0% Completed

Work order issued on 14-08-2024.

Kannur PH Dn EE
Date: 05/09/2024

Work has started | 0% Completed

Work order issued on 14-08-2024.

Kannur PH Dn EE
Date: 29/08/2024

Work has started | 0% Completed

Work order issued on 14-08-2024.

Perlasserry Sn 1
Date: 21/08/2024

Work has started | 0% Completed

work is not started yet

Perlasserry Sn 1
Date: 13/08/2024

Work has started | 0% Completed

work is not started yet

Perlasserry Sn 1
Date: 09/08/2024

Work has started | 0% Completed

work is not started yet

Perlasserry Sn 1
Date: 05/08/2024

Work has started | 0% Completed

work is not started yet

Perlasserry Sn 1
Date: 31/07/2024

Work has started | 0% Completed

work is not started yet

Perlasserry Sn 1
Date: 26/07/2024

Work has started | 0% Completed

work is not started yet

Perlasserry Sn 1
Date: 23/07/2024

Work has started | 0% Completed

not started

Perlasserry Sn 1
Date: 19/07/2024

Work has started | 0% Completed

not started

Kannur PH Dn EE
Date: 09/07/2024

Work has started | 0% Completed

Single bid received, submitted to SE for approval.

Perlasserry Sn 1
Date: 26/06/2024

Work has started | 0% Completed

Single bid received, submitted to SE for approval.

Perlasserry Sn 1
Date: 12/06/2024

Work in progress | 0% Completed

Single bid received, submitted to SE for approval.

Kannur PH Dn EE
Date: 04/06/2024

Work in progress | 0% Completed

Single bid received, submitted to SE for approval.

Kannur PH Dn EE
Date: 25/05/2024

Work has started | 0% Completed

Single bid received, submitted to SE for approval.

Kannur PH Dn EE
Date: 16/05/2024

Work in progress | 0% Completed

Single bid received, submitted to SE for approval.

Kannur PH Dn EE
Date: 03/05/2024

Work in progress | 0% Completed

Single bid received, submitted to SE for approval.

Kannur PH Dn EE
Date: 23/04/2024

Work in progress | 0% Completed

Tender under scrutiny.

Kannur PH Dn EE
Date: 15/04/2024

Work in progress | 0% Completed

Single bid received, negotiating with the contractor.

Perlasserry Sn 1
Date: 06/04/2024

Work has started | 0% Completed

Single bid received, negotiating with the contractor.

Perlasserry Sn 1
Date: 01/04/2024

Work has started | 0% Completed

Single bid received, negotiating with the contractor.

Kannur PH Dn EE
Date: 25/03/2024

Work in progress | 0% Completed

Single bid received, negotiating with the contractor.

Perlasserry Sn 1
Date: 13/03/2024

Work has started | 0% Completed

Due to no response tender extended with due date 18.03.2024

Kannur PH Dn EE
Date: 12/03/2024

Work in progress | 0% Completed

Due to no response tender extended with due date 18.03.2024

Perlasserry Sn 1
Date: 27/02/2024

Work has started | 0% Completed

Re-tender invited with due date 01.03.2024

Perlasserry Sn 1
Date: 22/02/2024

Work has started | 0% Completed

Re-tender invited with due date 01.03.2024

Kannur PH Dn EE
Date: 20/02/2024

Work in progress | 0% Completed

Re-tender invited with due date 01.03.2024

Perlasserry Sn 1
Date: 14/02/2024

Work has started | 0% Completed

Tender cancelled due to noresponse.

Perlasserry Sn 1
Date: 06/02/2024

Work has started | 0% Completed

Tender under Scrutiny

Perlasserry Sn 1
Date: 29/01/2024

Work has started | 0% Completed

Tender under Scrutiny

Perlasserry Sn 1
Date: 25/01/2024

Work has started | 0% Completed

Tender under scrutiny.

Kannur PH Dn EE
Date: 22/01/2024

Work in progress | 0% Completed

Tender under scrutiny.

Perlasserry Sn 1
Date: 10/01/2024

Work has started | 0% Completed

Work Tendered. Date of opening of tender-10.01.2024.

Kannur PH Dn EE
Date: 01/01/2024

Work has started | 0% Completed

Work Tendered. Date of opening of tender-10.01.2024.

Perlasserry Sn 1
Date: 21/12/2023

Work has started | 0% Completed

Estimate submitted and permission letter submitted to College of Engineering Thalassery for laying pipe line through its compound.

Perlasserry Sn 1
Date: 14/12/2023

Work has started | 0% Completed

Estimate submitted and permission letter submitted to College of Engineering Thalassery for laying pipe line through its compound.

Perlasserry Sn 1
Date: 08/12/2023

Work has started | 0% Completed

Estimate submitted

Perlasserry Sn 1
Date: 06/12/2023

Work has started | 0% Completed

estimate submitted

Perlasserry Sn 1
Date: 30/11/2023

Work has started | 0% Completed

estimate submitted

Perlasserry Sn 1
Date: 27/11/2023

Work has started | 0% Completed

estimate submitted

Perlasserry Sn 1
Date: 24/11/2023

Work has started | 0% Completed

estimate submitted

Perlasserry Sn 1
Date: 15/11/2023

Work has started | 0% Completed

estimate submitted

Kannur PH Dn EE
Date: 13/11/2023

Work in progress | 0% Completed

Estimate under scrutiny.

Perlasserry Sn 1
Date: 04/11/2023

Work in progress | 0% Completed

AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023 and detailed estimate submitted for approval.

Perlasserry Sn 1
Date: 31/10/2023

Work in progress | 0% Completed

AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023 and detailed estimate submitted for approval.

Perlasserry Sn 1
Date: 25/10/2023

Work in progress | 0% Completed

AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023 and detailed estimate submitted for approval.

Perlasserry Sn 1
Date: 16/10/2023

Work in progress | 0% Completed

AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023 and detailed estimate submitted for approval.

Kannur PH Dn EE
Date: 04/10/2023

Work in progress | 0% Completed

AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023 and detailed estimate submitted for approval

Kannur PH Dn EE
Date: 26/09/2023

Work has started | 0% Completed

AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023