| Perlasserry Sn 1 |
| Date: 21/04/2026 |
Work has been completed | 100% Completed
Work completed
| Perlasserry Sn 1 |
| Date: 15/04/2026 |
Work in progress | 95% Completed
Work in progress.
| Perlasserry Sn 1 |
| Date: 10/04/2026 |
Work in progress | 95% Completed
Work in progress
| Perlasserry Sn 1 |
| Date: 05/04/2026 |
Work in progress | 90% Completed
Work in progress. 90% completed.
| Perlasserry Sn 1 |
| Date: 30/03/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 25/03/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 21/03/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 17/03/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 10/03/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 07/03/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 02/03/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 27/02/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 22/02/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 19/02/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 11/02/2026 |
Work in progress | 80% Completed
Work in progress. 80% completed.
| Perlasserry Sn 1 |
| Date: 04/02/2026 |
Work in progress | 78% Completed
Work in progress. 78% completed.
| Perlasserry Sn 1 |
| Date: 31/01/2026 |
Work in progress | 78% Completed
Work in progress. 78% completed.
| Perlasserry Sn 1 |
| Date: 21/01/2026 |
Work in progress | 78% Completed
Work in progress. 78% completed.
| Perlasserry Sn 1 |
| Date: 17/01/2026 |
Work in progress | 78% Completed
Work in progress. 78% completed.
| Perlasserry Sn 1 |
| Date: 13/01/2026 |
Work in progress | 75% Completed
Work in progress. 75% completed.
| Perlasserry Sn 1 |
| Date: 06/01/2026 |
Work in progress | 75% Completed
Work in progress. 75% completed.
| Perlasserry Sn 1 |
| Date: 01/01/2026 |
Work in progress | 75% Completed
Work in progress. 75% completed.
| Perlasserry Sn 1 |
| Date: 26/12/2025 |
Work in progress | 70% Completed
Work in progress. 70% completed.
| Perlasserry Sn 1 |
| Date: 22/12/2025 |
Work in progress | 70% Completed
Work in progress. 70% completed.
| Perlasserry Sn 1 |
| Date: 16/12/2025 |
Work in progress | 70% Completed
Work in progress. 70% completed.
| Perlasserry Sn 1 |
| Date: 09/12/2025 |
Work in progress | 70% Completed
Work in progress. 70% completed.
| Perlasserry Sn 1 |
| Date: 03/12/2025 |
Work in progress | 70% Completed
Work in progress. 70% completed.
| Perlasserry Sn 1 |
| Date: 26/11/2025 |
Work in progress | 70% Completed
Work in progress. 70% completed.
| Perlasserry Sn 1 |
| Date: 19/11/2025 |
Work in progress | 65% Completed
Work in progress. 65% completed.
| Perlasserry Sn 1 |
| Date: 13/11/2025 |
Work in progress | 65% Completed
Work in progress. 60% completed.
| Perlasserry Sn 1 |
| Date: 06/11/2025 |
Work in progress | 60% Completed
Work in progress. 60% completed.
| Perlasserry Sn 1 |
| Date: 01/11/2025 |
Work in progress | 60% Completed
Work in progress. 60% completed.
| Perlasserry Sn 1 |
| Date: 28/10/2025 |
Work in progress | 60% Completed
Work in progress. 60% completed.
| Perlasserry Sn 1 |
| Date: 22/10/2025 |
Work in progress | 50% Completed
The work has resumed. Out of 2500m pipe line proposed , 1500m pipe line laying has been completed.
| Perlasserry Sn 1 |
| Date: 16/10/2025 |
Work in progress | 40% Completed
40% COMPLETED
| Perlasserry Sn 1 |
| Date: 26/09/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 18/09/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 12/09/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 08/09/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 27/08/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 21/08/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 14/08/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 08/08/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 02/08/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 28/07/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 16/07/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 10/07/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 08/07/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 02/07/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 28/06/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 24/06/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 17/06/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 09/06/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 16/05/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 07/05/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 29/04/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 19/04/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 15/04/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 10/04/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 01/04/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 24/03/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 17/03/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 27/02/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.
| Perlasserry Sn 1 |
| Date: 12/02/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 01/02/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 28/01/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 25/01/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 18/01/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 13/01/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath. 2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 04/01/2025 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.
| Perlasserry Sn 1 |
| Date: 31/12/2024 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.
| Perlasserry Sn 1 |
| Date: 21/12/2024 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.
| Perlasserry Sn 1 |
| Date: 17/12/2024 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.
| Perlasserry Sn 1 |
| Date: 10/12/2024 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.
| Perlasserry Sn 1 |
| Date: 03/12/2024 |
Work in progress | 25% Completed
The work has been temporarily stopped due to the objection from the panchayath.2500 M PIPE PROPOSED - 700 M COMPLETED.
| Perlasserry Sn 1 |
| Date: 27/11/2024 |
Work in progress | 25% Completed
The work has been stopped temporarily due to the objection from the panchayath.2500 M pipe proposed - 700 M completed.
| Perlasserry Sn 1 |
| Date: 13/11/2024 |
Work in progress | 25% Completed
The work has been stopped temporarily due to the objection from the panchayath.2500 M pipe proposed - 700 M completed.
| Perlasserry Sn 1 |
| Date: 06/11/2024 |
Work in progress | 25% Completed
The work has been stopped due to the objection from the panchayath.
| Perlasserry Sn 1 |
| Date: 02/11/2024 |
Work in progress | 25% Completed
2500M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 28/10/2024 |
Work in progress | 25% Completed
2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 22/10/2024 |
Work in progress | 25% Completed
2500 M PIPE PROPOSED - 700 M COMPLETED
| Perlasserry Sn 1 |
| Date: 19/10/2024 |
Work in progress | 25% Completed
700 m of pipe laid.
| Perlasserry Sn 1 |
| Date: 15/10/2024 |
Work in progress | 10% Completed
WORK IN PROGRESS
| Perlasserry Sn 1 |
| Date: 10/10/2024 |
Work in progress | 10% Completed
300m pipe laid.
| Kannur PH Dn EE |
| Date: 04/10/2024 |
Work has started | 0% Completed
Work order issued on 14-08-2024, agreement not executed.
| Kannur PH Dn EE |
| Date: 24/09/2024 |
Work has started | 0% Completed
Work order issued on 14-08-2024, agreement not executed.
| Perlasserry Sn 1 |
| Date: 11/09/2024 |
Work has started | 0% Completed
Work order issued on 14-08-2024.
| Kannur PH Dn EE |
| Date: 05/09/2024 |
Work has started | 0% Completed
Work order issued on 14-08-2024.
| Kannur PH Dn EE |
| Date: 29/08/2024 |
Work has started | 0% Completed
Work order issued on 14-08-2024.
| Perlasserry Sn 1 |
| Date: 21/08/2024 |
Work has started | 0% Completed
work is not started yet
| Perlasserry Sn 1 |
| Date: 13/08/2024 |
Work has started | 0% Completed
work is not started yet
| Perlasserry Sn 1 |
| Date: 09/08/2024 |
Work has started | 0% Completed
work is not started yet
| Perlasserry Sn 1 |
| Date: 05/08/2024 |
Work has started | 0% Completed
work is not started yet
| Perlasserry Sn 1 |
| Date: 31/07/2024 |
Work has started | 0% Completed
work is not started yet
| Perlasserry Sn 1 |
| Date: 26/07/2024 |
Work has started | 0% Completed
work is not started yet
| Perlasserry Sn 1 |
| Date: 23/07/2024 |
Work has started | 0% Completed
not started
| Perlasserry Sn 1 |
| Date: 19/07/2024 |
Work has started | 0% Completed
not started
| Kannur PH Dn EE |
| Date: 09/07/2024 |
Work has started | 0% Completed
Single bid received, submitted to SE for approval.
| Perlasserry Sn 1 |
| Date: 26/06/2024 |
Work has started | 0% Completed
Single bid received, submitted to SE for approval.
| Perlasserry Sn 1 |
| Date: 12/06/2024 |
Work in progress | 0% Completed
Single bid received, submitted to SE for approval.
| Kannur PH Dn EE |
| Date: 04/06/2024 |
Work in progress | 0% Completed
Single bid received, submitted to SE for approval.
| Kannur PH Dn EE |
| Date: 25/05/2024 |
Work has started | 0% Completed
Single bid received, submitted to SE for approval.
| Kannur PH Dn EE |
| Date: 16/05/2024 |
Work in progress | 0% Completed
Single bid received, submitted to SE for approval.
| Kannur PH Dn EE |
| Date: 03/05/2024 |
Work in progress | 0% Completed
Single bid received, submitted to SE for approval.
| Kannur PH Dn EE |
| Date: 23/04/2024 |
Work in progress | 0% Completed
Tender under scrutiny.
| Kannur PH Dn EE |
| Date: 15/04/2024 |
Work in progress | 0% Completed
Single bid received, negotiating with the contractor.
| Perlasserry Sn 1 |
| Date: 06/04/2024 |
Work has started | 0% Completed
Single bid received, negotiating with the contractor.
| Perlasserry Sn 1 |
| Date: 01/04/2024 |
Work has started | 0% Completed
Single bid received, negotiating with the contractor.
| Kannur PH Dn EE |
| Date: 25/03/2024 |
Work in progress | 0% Completed
Single bid received, negotiating with the contractor.
| Perlasserry Sn 1 |
| Date: 13/03/2024 |
Work has started | 0% Completed
Due to no response tender extended with due date 18.03.2024
| Kannur PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 0% Completed
Due to no response tender extended with due date 18.03.2024
| Perlasserry Sn 1 |
| Date: 27/02/2024 |
Work has started | 0% Completed
Re-tender invited with due date 01.03.2024
| Perlasserry Sn 1 |
| Date: 22/02/2024 |
Work has started | 0% Completed
Re-tender invited with due date 01.03.2024
| Kannur PH Dn EE |
| Date: 20/02/2024 |
Work in progress | 0% Completed
Re-tender invited with due date 01.03.2024
| Perlasserry Sn 1 |
| Date: 14/02/2024 |
Work has started | 0% Completed
Tender cancelled due to noresponse.
| Perlasserry Sn 1 |
| Date: 06/02/2024 |
Work has started | 0% Completed
Tender under Scrutiny
| Perlasserry Sn 1 |
| Date: 29/01/2024 |
Work has started | 0% Completed
Tender under Scrutiny
| Perlasserry Sn 1 |
| Date: 25/01/2024 |
Work has started | 0% Completed
Tender under scrutiny.
| Kannur PH Dn EE |
| Date: 22/01/2024 |
Work in progress | 0% Completed
Tender under scrutiny.
| Perlasserry Sn 1 |
| Date: 10/01/2024 |
Work has started | 0% Completed
Work Tendered. Date of opening of tender-10.01.2024.
| Kannur PH Dn EE |
| Date: 01/01/2024 |
Work has started | 0% Completed
Work Tendered. Date of opening of tender-10.01.2024.
| Perlasserry Sn 1 |
| Date: 21/12/2023 |
Work has started | 0% Completed
Estimate submitted and permission letter submitted to College of Engineering Thalassery for laying pipe line through its compound.
| Perlasserry Sn 1 |
| Date: 14/12/2023 |
Work has started | 0% Completed
Estimate submitted and permission letter submitted to College of Engineering Thalassery for laying pipe line through its compound.
| Perlasserry Sn 1 |
| Date: 08/12/2023 |
Work has started | 0% Completed
Estimate submitted
| Perlasserry Sn 1 |
| Date: 06/12/2023 |
Work has started | 0% Completed
estimate submitted
| Perlasserry Sn 1 |
| Date: 30/11/2023 |
Work has started | 0% Completed
estimate submitted
| Perlasserry Sn 1 |
| Date: 27/11/2023 |
Work has started | 0% Completed
estimate submitted
| Perlasserry Sn 1 |
| Date: 24/11/2023 |
Work has started | 0% Completed
estimate submitted
| Perlasserry Sn 1 |
| Date: 15/11/2023 |
Work has started | 0% Completed
estimate submitted
| Kannur PH Dn EE |
| Date: 13/11/2023 |
Work in progress | 0% Completed
Estimate under scrutiny.
| Perlasserry Sn 1 |
| Date: 04/11/2023 |
Work in progress | 0% Completed
AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023 and detailed estimate submitted for approval.
| Perlasserry Sn 1 |
| Date: 31/10/2023 |
Work in progress | 0% Completed
AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023 and detailed estimate submitted for approval.
| Perlasserry Sn 1 |
| Date: 25/10/2023 |
Work in progress | 0% Completed
AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023 and detailed estimate submitted for approval.
| Perlasserry Sn 1 |
| Date: 16/10/2023 |
Work in progress | 0% Completed
AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023 and detailed estimate submitted for approval.
| Kannur PH Dn EE |
| Date: 04/10/2023 |
Work in progress | 0% Completed
AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023 and detailed estimate submitted for approval
| Kannur PH Dn EE |
| Date: 26/09/2023 |
Work has started | 0% Completed
AS accorded vide AS No. KWA-JB/598/2023-AE 2 on 14.08.2023