JJM - Part 1- Providing Water Supply Connections To Households From The Existing Distribution Mains in Udayamperoor Panchayath and Allied Work (1000 FHTC)
| Project |
JJM - Part 1- Providing Water Supply Connections To Households From The Existing Distribution Mains in Udayamperoor Panchayath and Allied Work (1000 FHTC) |
| Project Code |
EKMJJM08203712 |
| Type |
Main project |
| Funding Agency |
JJM |
| Category |
JJM |
Type of scheme |
Water Supply |
| Description |
JJM - Part 1- Providing Water Supply Connections To Households From The Existing Distribution Mains in Udayamperoor Panchayath and Allied Work (1000 FHTC) |
| Status |
On-going |
| District |
Ernakulam |
| Executing Office |
Kochi WS Dn |
| AS Amount (Rs) |
23900000
|
| AS Number |
G.O(Rt)No.541/2020/WRD |
| TS Amount (Rs) |
23400000 |
| TS Number |
TS/2020-2021/2020/13529, SE PH Circle kochi |
| Total Bill Submitted (Rs) |
3928780 |
| Total Bill Paid (Rs) |
2710363 |
| Population Benefitted |
5000 |
| Capacity in MLD |
0.20 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
Udayamperoor Panchayath |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
JJM - Part 1- Providing Water Supply Connections To Households From The Existing Distribution Mains in Udayamperoor Panchayath and Allied Work. (1000FHTC) |
Trippunnithura WS Sn 1 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 26 Aug 2021 |
680 FHTC given and bill under preparation |
Thripunithura WS Sn - AE 1 |
|
| 08 Aug 2021 |
600 FHTC given |
Thripunithura WS Sn - AE 1 |
|
| 20 Jul 2021 |
550 FHTC given |
Thripunithura WS Sn - AE 1 |
|
| 15 Jul 2021 |
540 FHTC given |
Thripunithura WS Sn - AE 1 |
|
| 14 Jul 2021 |
CC 6th and part bill submitted (150 FHTC/476 FHTC) |
Thripunithura WS Sn - AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
31/12/2020 |
| Scheduled date of Completion of the Project |
26 May 2021 |
| Expected date of Completion |
30/09/2021 |
Processing Dates
| AS Date |
21 Aug 2020 |
| TS Date |
27 Aug 2020 |