| Project |
JJM-Providing retrofittable/extendable water service connections in Thrikkunnapuzha Panchayath in Alappuzha District-work 2 |
| Project Code |
ALPJJM08207613 |
| Type |
Main project |
| Funding Agency |
JJM |
| Category |
JJM |
Type of scheme |
Water Supply |
| Description |
Providing FHTC 75Nos to to Thrikkunnappuzha Panchayat |
| Status |
On-going |
| District |
Alappuzha |
| Executing Office |
Alappuzha Project Dn |
| AS Amount (Rs) |
8420000
|
| AS Number |
GO(rt) 541/2020/wrd dtd 21.08.20 |
| TS Amount (Rs) |
1124000 |
| TS Number |
ts/2020-21/2020/15339 d416 td 28/01/21 |
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
50000 |
| Capacity in MLD |
20.00 |
| Actual Project Completion Date |
30 Jul 2021 |
| Coverage |
Providing FHTC 75Nos to to Thrikkunnappuzha Panchayat |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
JJM-Providing retrofittable/extendable water service connections in Thrikkunnapuzha Panchayath in Alappuzha District-work 2 |
Alappuzha Project Dn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 09 Aug 2021 |
66/75 FHTC COMPLETED. main line work under progress |
Alappuzha Proj AE |
|
| 30 Jul 2021 |
66/75 FHTC COMPLETED |
Alappuzha Proj AE |
|
| 28 Jul 2021 |
64/75 FHTC COMPLETED |
Alappuzha Proj AE |
|
| 22 Jul 2021 |
54/75 FHTC COMPLETED |
Alappuzha Proj AE |
|
| 17 Jul 2021 |
44/75 FHTC COMPLETED |
Alappuzha Proj AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
01/07/2021 |
| Scheduled date of Completion of the Project |
26 Jun 2021 |
| Expected date of Completion |
31/07/2021 |
Processing Dates
| AS Date |
21 Aug 2020 |
| TS Date |
28 Jan 2021 |