| Project | Plan 2020-21- RWSS to Oriyera - Supplying and installation of pump set |
|---|---|
| Project Code | KGDGOK10205862 |
| Type | Main project |
| Funding Agency | GOK |
| Category | State plan | Type of scheme | Water Supply |
| Description | Supply and erection of pump |
| Status | On-going |
| District | Kasaragod |
| Executing Office | Kasargod PH Dn |
| AS Amount (Rs) | 50000 |
| AS Number | KWA/JB/P4/9/2020-21(XI) |
| TS Amount (Rs) | 50000 |
| TS Number | TS/2020-2021/2020/12010 |
| Total Bill Submitted (Rs) | |
| Total Bill Paid (Rs) | |
| Population Benefitted | |
| Capacity in MLD | |
| Actual Project Completion Date | Date is not specified |
| Coverage |
| Date of start of Project | Date is not specified |
|---|---|
| Scheduled date of Completion of the Project | Date is not specified |
| Expected date of Completion | 31/12/2021 |
| AS Date | 08 Oct 2020 |
|---|---|
| TS Date | 29 Dec 2020 |
| Project Officers | View |
|---|