State Plan 2021-22 EMWSS- Removing filter media and repacking with anthracite dual media and in bed no.8 at plant No.3Head works Aluva
| Project |
State Plan 2021-22 EMWSS- Removing filter media and repacking with anthracite dual media and in bed no.8 at plant No.3Head works Aluva |
| Project Code |
EKMGOK06217656 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
Type of scheme |
Water Supply |
| Description |
State plan 2021-22 EMWSS- Removing filter media and repacking with anthracite dual media and in bed no.8 at plant No.3Head works Aluva |
| Status |
On-going |
| District |
Ernakulam |
| Executing Office |
Aluva PH Dn |
| AS Amount (Rs) |
4420000
|
| AS Number |
PIU1/SP/18/2021-22 |
| TS Amount (Rs) |
|
| TS Number |
|
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
Date is not specified |
| Coverage |
|
Packages
| No. |
Project Name |
Location |
View |
| 1 |
EMWSS- Removing filter media and repacking with anthracite dual media and in bed no.8 at plant No.3Head works Aluva |
Aluva HW Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 23 Sep 2021 |
Estimate under CE,s Office |
Aluva AE HW |
|
| 20 Sep 2021 |
Estimate under CE,s Office |
Aluva AE HW |
|
| 17 Sep 2021 |
Estimate under CE,s Office |
Aluva AE HW |
|
| 15 Sep 2021 |
Estimate under CE,s Office |
Aluva AE HW |
|
| 13 Sep 2021 |
Estimate under CE,s Office |
Aluva AE HW |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
16/06/2021 |
| Scheduled date of Completion of the Project |
31 Dec 2021 |
| Expected date of Completion |
31/12/2021 |