KIIFB 2017-18- Drinking water project in Ettumanoor Municipality-Package 3

Project KIIFB 2017-18- Drinking water project in Ettumanoor Municipality-Package 3
Project Code KTMKIIFB0619525P3
Type Package
Main Project KIIFB 2017-18- Drinking water project in Ettumanoor Municipality
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Description Package-IIIDistribution to Zone-3(Part), CWGM from OHSR at Tp site to Boosting statin at Ettumanoor, OHSR at Kattachira, Gravity conveyance main etc
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
TS Amount (Rs)
TS Number
Technical specification CWGM from WTP to Boosting station at Ettumanoor- 350mm DI K-9-1600m, .5LL OHSR at Kattachira(Demishing old .5LL GLSR), Distributiion distribution network in Zone 3-Peroor(Part)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/03/2023

Processing Dates

AS Date 21 Jun 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

AE3 ktm
Date: 17/03/2021

Work has started | 0% Completed

Estimate for the package is send for review and approval.

AE3 ktm
Date: 15/03/2021

Work has started | 0% Completed

Estimate send for review and approval.