| Project | KIIFB 2017-18- Drinking water project in Ettumanoor Municipality-Package 2 |
|---|---|
| Project Code | KTMKIIFB0619525P2 |
| Type | Package |
| Main Project | KIIFB 2017-18- Drinking water project in Ettumanoor Municipality |
| Funding Agency | KIIFB |
| Category | KIIFB WATER SUPPLY SCHEME | Type of scheme | Water Supply |
| Description | OHSR at Kacherikunnu, CWPM to Kacherikunnu, Distribution from OHSR at Carithas, Retaining wall at Carithas, CWGM to OHSR at Carithas |
| Status | On-going |
| District | Kottayam |
| Executing Office | Kottayam Project Dn |
| TS Amount (Rs) | |
| TS Number | |
| Technical specification | 10LL OHSR at Carithas(permissive sanction to be obtained). CWGM from WTP to Carithas- 300MM DI K-9, CWPM to Kacherikunnu-350mm DI K-9, Distributionnetwork using 160mm PVC and 90mm PVC for Ettumanoor Municipality and Athirampuzha panchayat from Kacherikunnu OHSR and Carithas OHSR |
Project Progress Status |
Project Progress Status |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 31/03/2023 |
| AS Date | 21 Jun 2019 |
|---|
| AE3 ktm |
| Date: 17/03/2021 |
Work has started | 0% Completed
Permissive sanction for LA for construction of OHSR at Kacherikunnu is pending at RDO office. Estimate for the package is send for review and approval.
| AE3 ktm |
| Date: 16/03/2021 |
Work has started | 0% Completed
Permissive sanction for LA for construction of OHSR is pending at RDO.