- Home
- STATE PLAN 2018- 19- CWSS TO KAYAMKULAM...
STATE PLAN 2018- 19- CWSS TO KAYAMKULAM AND ARATTUPUZHA - SUPPLY, ERECTION AND COMMISSIONING OF 75 HP C/F PUMP SET ( FOR WSS TO ARATTUPUZHA ) AT CLEAR WATER PUMP HOUSE OF PATHIYOOR WTP.
| Project |
STATE PLAN 2018- 19- CWSS TO KAYAMKULAM AND ARATTUPUZHA - SUPPLY, ERECTION AND COMMISSIONING OF 75 HP C/F PUMP SET ( FOR WSS TO ARATTUPUZHA ) AT CLEAR WATER PUMP HOUSE OF PATHIYOOR WTP. |
| Project Code |
ALPGOK08187897 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
Type of scheme |
Water Supply |
| Description |
STATE PLAN 2018- 19- CWSS TO KAYAMKULAM AND ARATTUPUZHA - SUPPLY, ERECTION AND COMMISSIONING OF 75 HP C/F PUMP SET ( FOR WSS TO ARATTUPUZHA ) AT CLEAR WATER PUMP HOUSE OF PATHIYOOR WTP.
|
| Status |
On-going |
| District |
Alappuzha |
| Executing Office |
Alappuzha PH Dn |
| AS Amount (Rs) |
1370000
|
| AS Number |
G.O.(Rt)No.615/2018/WRD Dated,Thiruvanthapuram,20/8/2018 |
| TS Amount (Rs) |
1256000 |
| TS Number |
TS/2018-2019/2018/2477 Dated: 04-02-2019 |
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
20000 |
| Capacity in MLD |
12.00 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
ARATTUPUZHA |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
STATE PLAN 2018- 19- CWSS TO KAYAMKULAM AND ARATTUPUZHA - SUPPLY, ERECTION AND COMMISSIONING OF 75 HP C/F PUMP SET ( FOR WSS TO ARATTUPUZHA ) AT CLEAR WATER PUMP HOUSE OF PATHIYOOR WTP. |
Kayamkulam PH Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 05 Sep 2021 |
Tender process in progress |
Kayamkulam AE |
|
| 29 Aug 2021 |
Tender process in progress |
Kayamkulam AE |
|
| 24 Aug 2021 |
Tender process in progress |
Kayamkulam AE |
|
| 22 Aug 2021 |
Tender process in progress |
Kayamkulam AE |
|
| 16 Aug 2021 |
Tender process in progress |
Kayamkulam AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
Date is not specified |
| Scheduled date of Completion of the Project |
Date is not specified |
| Expected date of Completion |
31/12/2021 |
Processing Dates
| AS Date |
20 Aug 2018 |
| TS Date |
04 Feb 2019 |