KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District-Package 1

Project KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District-Package 1
Project Code TCRKIIFB1118498P1
Type Package
Main Project KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Description Package -I a) 9m dia Intakewell cum pump house at Vettilappara b) Raw water pumpset-330 HP -2 Nos c) RWPM 450mm DI K9-4900m d)12 MLD WTP at Pillappara e) 2LL OHSR for Athirapilly f) Clear water pumpset at Athirapilly- 7.5HP-2Nos g) 150mm CWPM to Athirapilly Tank -50m h) 450mm DI K9 CWGM to 1st Common Junction (Vettikuzhy)-10230M i) 500kVA Transformer at Intakewell site j)100 kVA Transformer at WTP site k) Crane facility, SCADA l) Site leveling & Retaining wall at WTP site m) Road restoration works
Status On-going
District Thrissur
Executing Office Nattika Project Dn
TS Amount (Rs) 403600000
TS Number TS/2019-2020/2019/17186 Dated: 22.11.2019
Technical specification Ratio of material and labor - 1.04

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 20/07/2020
Scheduled date of Completion as per agreement 28 Jun 2022
Expected date of Completion 28/06/2022

Processing Dates

TS Date 22 Nov 2019
Estimate Approval 22 Nov 2019
NIT Approval 27 Nov 2019
Tender Closing 30 Dec 2019
Technichal Pre-Qualification 23 Jan 2020
Price bid opening 03 Jan 2020

Approval Dates

Workorder Date 29 Jun 2020
Agreement Date 14 Jul 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

AE3 ntka
Date: 16/06/2021

Work in progress | 11% Completed

WTP-Rock blasting is in progress. Intake Well- Forest Range officer inspected site. Pipe supply 450 mm DI K9= 5423.0m Pipe laying 450mm DI K9 RWPM= 1168.5m, CWGM= 1314.5m.

AE3 ntka
Date: 15/06/2021

Work in progress | 11% Completed

WTP-Rock blasting is in progress. Intake Well- Forest Range officer inspected site. Pipe supply 450 mm DI K9= 5423.0m Pipe laying 450mm DI K9 RWPM= 733.5m, CWGM= 1028.5m.