KIIFB 2017-18- Drinking water project in Ettumanoor Municipality Package IV

Project KIIFB 2017-18- Drinking water project in Ettumanoor Municipality Package IV
Project Code KTMKIIFB0619525P4
Type Package
Main Project KIIFB 2017-18- Drinking water project in Ettumanoor Municipality
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Description Package-IV Distribution to Zone -3(Part), Distribution from OHSR at Kattachira Zone 6-7950CWGM from OHSR at TP site to Kattachira, Gravity conveyance main to existing OHSR at mangalamkunnu
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
TS Amount (Rs) 117440000
TS Number TS/2019-2020/2019/19040
Technical specification Clear water gravity main to Kattachira - 150mm DI K9 - 7850m, Distribution net work through NH Roads and Distribution net work in Kattachira area 160mm PVC 8 Kg

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 11/09/2020
Scheduled date of Completion as per agreement 30 Jun 2021
Expected date of Completion 30/06/2021

Processing Dates

TS Date 31 Jan 2020
Estimate Approval 31 Jan 2020
NIT Approval 31 Jan 2020
Tender Closing 21 May 2020
Technichal Pre-Qualification 21 May 2020
Price bid opening 21 May 2020

Approval Dates

Workorder Date 01 Jul 2020
Agreement Date 15 Jul 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

AE3 ktm
Date: 10/06/2021

Work in progress | 53% Completed

Total pipe required 37.6 Kms Pipe Supplied 21.6 Kms Pipe Laid 18.4 Kms direction issued to the contractor on 18/5/ 21 to supply balance pipe and resume the work after the joint meeting with PWD in the presence of Hon Minister Sri V N Vasavan, MLA of the LA Ettumanoor..

AE3 ktm
Date: 09/06/2021

Work in progress | 53% Completed

Total pipe required 37.6 Kms Pipe Supplied 21.6 Kms Pipe Laid 18.4 Kms direction issued to the contractor on 18/5/ 21 to supply balance pipe and resume the work after the joint meeting with PWD in the presence of Hon Minister Sri V N Vasavan, MLA of the LA Ettumanoor..