State Plan 2021-22 Optimization of Production and Transmission - Renovation of WTP - Augmentation of WSS to Thripunithura municipality and adjoining panchayaths - Providing back wash reusing arrangement for 46 MLD plant at Choondy
| Project |
State Plan 2021-22 Optimization of Production and Transmission - Renovation of WTP - Augmentation of WSS to Thripunithura municipality and adjoining panchayaths - Providing back wash reusing arrangement for 46 MLD plant at Choondy |
| Project Code |
EKMGOK06217692 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
Type of scheme |
Water Supply |
| Description |
State Plan 2021-22 Optimization of Production and Transmission - Renovation of WTP - Augmentation of WSS to Thripunithura municipality and adjoining panchayaths - Providing back wash reusing arrangement for 46 MLD plant at Choondy |
| Status |
On-going |
| District |
Ernakulam |
| Executing Office |
Kochi WS Dn |
| AS Amount (Rs) |
3500000
|
| AS Number |
KWA/JB/PIU-1/AE4/State plan/OPT/05/2021-22 |
| TS Amount (Rs) |
3500000 |
| TS Number |
|
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
25000 |
| Capacity in MLD |
3.00 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
poothrikka,thiruvaniyoor,aickaranadu and vadavukodu puthencruz |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
State Plan 2021-22 Optimization of Production and Transmission - Renovation of WTP - Augmentation of WSS to Thripunithura municipality and adjoining panchayaths - Providing back wash reusing arrangement for 46 MLD plant at Choondy |
Puthencruz WS Sn 2 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 22 Sep 2021 |
Estimate under scrutiny in section office |
Puthencruz IWS Sn - AE 2 |
|
| 22 Sep 2021 |
Estimate handed over to AE for incorporating necessary corrections & to resubmit |
Puthencruz WS Sub Dn - AEE |
|
| 21 Sep 2021 |
Estimate submitted limiting the AS amount |
Puthencruz IWS Sn - AE 2 |
|
| 21 Sep 2021 |
Estimate limiting the AS amount and submitted to AEE |
Puthencruz WS Sub Dn - AEE |
|
| 18 Sep 2021 |
Estimate under scrutiny in section office |
Puthencruz IWS Sn - AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
Date is not specified |
| Scheduled date of Completion of the Project |
Date is not specified |
| Expected date of Completion |
31/12/2021 |