Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State Plan 2021-22 Optimization of Production and Transmission - Renovation of WTP - Augmentation of WSS to Thripunithura municipality and adjoining panchayaths - Providing back wash reusing arrangement for 46 MLD plant at Choondy

Project State Plan 2021-22 Optimization of Production and Transmission - Renovation of WTP - Augmentation of WSS to Thripunithura municipality and adjoining panchayaths - Providing back wash reusing arrangement for 46 MLD plant at Choondy
Project Code EKMGOK06217692
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Description State Plan 2021-22 Optimization of Production and Transmission - Renovation of WTP - Augmentation of WSS to Thripunithura municipality and adjoining panchayaths - Providing back wash reusing arrangement for 46 MLD plant at Choondy
Status On-going
District Ernakulam
Executing Office Kochi WS Dn
AS Amount (Rs) 3500000
AS Number KWA/JB/PIU-1/AE4/State plan/OPT/05/2021-22
TS Amount (Rs) 3500000
TS Number
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 25000
Capacity in MLD 3.00
Actual Project Completion Date Date is not specified
Coverage poothrikka,thiruvaniyoor,aickaranadu and vadavukodu puthencruz
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan 2021-22 Optimization of Production and Transmission - Renovation of WTP - Augmentation of WSS to Thripunithura municipality and adjoining panchayaths - Providing back wash reusing arrangement for 46 MLD plant at Choondy Puthencruz WS Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Sep 2021 Estimate under scrutiny in section office Puthencruz IWS Sn - AE 2
22 Sep 2021 Estimate handed over to AE for incorporating necessary corrections & to resubmit Puthencruz WS Sub Dn - AEE
21 Sep 2021 Estimate submitted limiting the AS amount Puthencruz IWS Sn - AE 2
21 Sep 2021 Estimate limiting the AS amount and submitted to AEE Puthencruz WS Sub Dn - AEE
18 Sep 2021 Estimate under scrutiny in section office Puthencruz IWS Sn - AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 31/12/2021

Processing Dates

AS Date 16 Jun 2021

Other details

Project Officers View

Location