KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District- Package-2

Project KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District- Package-2
Project Code TCRKIIFB1118498P2
Type Package
Main Project KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Description Package -II a) 20LL OHSR at Chembankunnu b) 250mm DI K9 CWGM to Chembankunnu- 2100m c) 350mm DI K9 CWGM - 1500M d) 14LL OHSR at Orappana e) 250mm DI K9 CWGM to Pariyaram -7340m f) 1LL OHSR at Chaipankuzhy (Kodassery High Level) g) 100mm DI K9 CWPM-370m h) Booster pump house with 5HP Booster pumpset i) Road restoration works
Status On-going
District Thrissur
Executing Office Nattika Project Dn
TS Amount (Rs) 182500000
TS Number TS/2019-2020/2019/17187 Dated: 22.11.2019
Technical specification Ratio of material and labor - 0.42

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 11/09/2020
Scheduled date of Completion as per agreement 28 Jun 2022
Expected date of Completion 28/06/2022

Processing Dates

TS Date 22 Nov 2019
Estimate Approval 22 Nov 2019
NIT Approval 27 Nov 2019
Tender Closing 30 Dec 2019
Technichal Pre-Qualification 23 Jan 2020
Price bid opening 03 Jan 2020

Approval Dates

Workorder Date 29 Jun 2020
Agreement Date 14 Jul 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

AE3 ntka
Date: 16/06/2021

Work in progress | 60% Completed

14LL OHSR- Floor beam and slab reinforcement and RCC work completed. Earth filling upto Plinth beam in progress. 1LL OHSR- Reinforcement & RCC of roof slab and Staircase completed. Handrail work completed. Water tightness test completed. 20LL OHSR- Footing PCC completed. Reinforcement & shuttering work of footing in progress. Pipe Supply - 350mm DI K-9 Pipe -1530m , 250mm DI K-9 Pipe- 9658m, 100mm DI K-9 Pipe- 374m & 100mm DI K-7 Pipe-49.5m completed. Pipe Laying- 350mm DI-1489.2m, 250mm DI-8475.0m and 100mm DI- 329.5m completed. Valve chambers 4nos completed. GSB & WMM laying in progress at LSGD & District panchayath roads in progress..

AE3 ntka
Date: 15/06/2021

Work in progress | 60% Completed

14LL OHSR- Floor beam and slab reinforcement and RCC work completed. Earth filling upto Plinth beam in progress. 1LL OHSR- Reinforcement & RCC of roof slab and Staircase completed. Handrail work completed. Water tightness test completed. 20LL OHSR- Footing PCC completed. Reinforcement & shuttering work of footing in progress. Pipe Supply - 350mm DI K-9 Pipe -1530m , 250mm DI K-9 Pipe- 9658m, 100mm DI K-9 Pipe- 374m & 100mm DI K-7 Pipe-49.5m completed. Pipe Laying- 350mm DI-1489.2m, 250mm DI-7871.0m and 100mm DI- 329.5m completed. Valve chambers 4nos completed. GSB & WMM laying in progress at LSGD & District panchayath roads in progress..