| Project | KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District- Package-2 |
|---|---|
| Project Code | TCRKIIFB1118498P2 |
| Type | Package |
| Main Project | KIIFB- WSS to Kodassery, Pariyaram and Athirappally Panchayaths in Thrissur District |
| Funding Agency | KIIFB |
| Category | KIIFB | Type of scheme | Water Supply |
| Description | Package -II a) 20LL OHSR at Chembankunnu b) 250mm DI K9 CWGM to Chembankunnu- 2100m c) 350mm DI K9 CWGM - 1500M d) 14LL OHSR at Orappana e) 250mm DI K9 CWGM to Pariyaram -7340m f) 1LL OHSR at Chaipankuzhy (Kodassery High Level) g) 100mm DI K9 CWPM-370m h) Booster pump house with 5HP Booster pumpset i) Road restoration works |
| Status | On-going |
| District | Thrissur |
| Executing Office | Nattika Project Dn |
| TS Amount (Rs) | 182500000 |
| TS Number | TS/2019-2020/2019/17187 Dated: 22.11.2019 |
| Technical specification | Ratio of material and labor - 0.42 |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 11/09/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 28 Jun 2022 |
| Expected date of Completion | 28/06/2022 |
| TS Date | 22 Nov 2019 |
|---|---|
| Estimate Approval | 22 Nov 2019 |
| NIT Approval | 27 Nov 2019 |
| Tender Closing | 30 Dec 2019 |
| Technichal Pre-Qualification | 23 Jan 2020 |
| Price bid opening | 03 Jan 2020 |
| Workorder Date | 29 Jun 2020 |
|---|---|
| Agreement Date | 14 Jul 2020 |
| AE3 ntka |
| Date: 16/06/2021 |
Work in progress | 60% Completed
14LL OHSR- Floor beam and slab reinforcement and RCC work completed. Earth filling upto Plinth beam in progress. 1LL OHSR- Reinforcement & RCC of roof slab and Staircase completed. Handrail work completed. Water tightness test completed. 20LL OHSR- Footing PCC completed. Reinforcement & shuttering work of footing in progress. Pipe Supply - 350mm DI K-9 Pipe -1530m , 250mm DI K-9 Pipe- 9658m, 100mm DI K-9 Pipe- 374m & 100mm DI K-7 Pipe-49.5m completed. Pipe Laying- 350mm DI-1489.2m, 250mm DI-8475.0m and 100mm DI- 329.5m completed. Valve chambers 4nos completed. GSB & WMM laying in progress at LSGD & District panchayath roads in progress..
| AE3 ntka |
| Date: 15/06/2021 |
Work in progress | 60% Completed
14LL OHSR- Floor beam and slab reinforcement and RCC work completed. Earth filling upto Plinth beam in progress. 1LL OHSR- Reinforcement & RCC of roof slab and Staircase completed. Handrail work completed. Water tightness test completed. 20LL OHSR- Footing PCC completed. Reinforcement & shuttering work of footing in progress. Pipe Supply - 350mm DI K-9 Pipe -1530m , 250mm DI K-9 Pipe- 9658m, 100mm DI K-9 Pipe- 374m & 100mm DI K-7 Pipe-49.5m completed. Pipe Laying- 350mm DI-1489.2m, 250mm DI-7871.0m and 100mm DI- 329.5m completed. Valve chambers 4nos completed. GSB & WMM laying in progress at LSGD & District panchayath roads in progress..