PART III. Laying Interconnection sewer networks (for Household connections): from trunk main Man Holes on both sides of the road from Arasumoodu

Project PART III. Laying Interconnection sewer networks (for Household connections): from trunk main Man Holes on both sides of the road from Arasumoodu
Project Code TVMAMRUT0818645P3
Type Package
Main Project AMRUT TSS- Laying Transmission main and sewer networks in Block J (Karimanal) Collection and Conveyance system- ( 3 packages)
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Description for Household connections : from trunk main Man Holes on both sides of the road from Arasumoodu to edathara to avoid futher cutting of the road.
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
TS Amount (Rs) 7000000
TS Number 1839/2019-20
Technical specification House connection pits both sides- Laying & connecting 300 numbers of house connection pits.)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 11/09/2019
Scheduled date of Completion as per agreement 15 Apr 2021
Expected date of Completion 31/08/2021

Processing Dates

TS Date 11 Jul 2019
Estimate Approval 11 Jul 2019
NIT Approval 20 Nov 2019
Tender Closing 12 Apr 2019
Technichal Pre-Qualification 04 Dec 2019
Price bid opening 04 Dec 2019

Approval Dates

Workorder Date 16 Oct 2020
Agreement Date 04 Nov 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

AEE5 Project TVM
Date: 06/07/2021

Work in progress | 19% Completed

Work is still pending , due to not laying main transmission line by the Firm M/s.Vardhaman Engineering works..

AEE5 Project TVM
Date: 05/07/2021

Work in progress | 19% Completed

124nos of small connection pits works done out of 300 nos .The interconnection works can be executed on the progress of the main transmission pipe line & MH works of the contractor M/s Varthaman Engg works .The progress of the Work in laying transmission main is nil for the last Two week.