| Project | PART III. Laying Interconnection sewer networks (for Household connections): from trunk main Man Holes on both sides of the road from Arasumoodu |
|---|---|
| Project Code | TVMAMRUT0818645P3 |
| Type | Package |
| Main Project | AMRUT TSS- Laying Transmission main and sewer networks in Block J (Karimanal) Collection and Conveyance system- ( 3 packages) |
| Funding Agency | AMRUT |
| Category | AMRUT | Type of scheme | Water Supply |
| Description | for Household connections : from trunk main Man Holes on both sides of the road from Arasumoodu to edathara to avoid futher cutting of the road. |
| Status | On-going |
| District | Thiruvananthapuram |
| Executing Office | Trivandrum Project Dn |
| TS Amount (Rs) | 7000000 |
| TS Number | 1839/2019-20 |
| Technical specification | House connection pits both sides- Laying & connecting 300 numbers of house connection pits.) |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 11/09/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 15 Apr 2021 |
| Expected date of Completion | 31/08/2021 |
| TS Date | 11 Jul 2019 |
|---|---|
| Estimate Approval | 11 Jul 2019 |
| NIT Approval | 20 Nov 2019 |
| Tender Closing | 12 Apr 2019 |
| Technichal Pre-Qualification | 04 Dec 2019 |
| Price bid opening | 04 Dec 2019 |
| Workorder Date | 16 Oct 2020 |
|---|---|
| Agreement Date | 04 Nov 2020 |
| AEE5 Project TVM |
| Date: 06/07/2021 |
Work in progress | 19% Completed
Work is still pending , due to not laying main transmission line by the Firm M/s.Vardhaman Engineering works..
| AEE5 Project TVM |
| Date: 05/07/2021 |
Work in progress | 19% Completed
124nos of small connection pits works done out of 300 nos .The interconnection works can be executed on the progress of the main transmission pipe line & MH works of the contractor M/s Varthaman Engg works .The progress of the Work in laying transmission main is nil for the last Two week.