| Project | Jal Jeevan Mission- Kasaragod District- Vorkady Panchayath- WSS to Vorkady and adjoining Villages- Phase II - Laying distribution System and providing FHTC- Package |
|---|---|
| Project Code | KGDJJM08202950P1 |
| Type | Package |
| Main Project | Jal Jeevan Mission- Kasaragod District- Vorkady Panchayath- WSS to Vorkady and adjoining Villages- Phase II - Laying distribution System and providing FHTC |
| Funding Agency | JJM |
| Category | JJM | Type of scheme | Water Supply |
| Description | Providing FHTC |
| Status | On-going |
| District | Kasaragod |
| Executing Office | Kumbala PH Sn |
| TS Amount (Rs) | 85700000 |
| TS Number | TS/2020-2021/2020/14613 |
| Technical specification | WSS to Vorkady and adjoining Villages |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 30/11/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 12 Apr 2021 |
| Expected date of Completion | 30/07/2021 |
| TS Date | 27 Aug 2020 |
|---|---|
| Estimate Approval | 27 Aug 2020 |
| Tender Closing | 26 Sep 2020 |
| Price bid opening | 08 Oct 2020 |
| Workorder Date | 13 Oct 2020 |
|---|---|
| Agreement Date | 22 Oct 2020 |
| Kumbala PH Sn AE |
| Date: 05/08/2021 |
Work in progress | 72% Completed
On going.
| Kumbala PH Sn AE |
| Date: 01/08/2021 |
Work in progress | 72% Completed
on going.