Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths-Package I |
---|---|
Project Code | PTAKIIFB0117560P1 |
Type | Package |
Main Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | This package includes Construction of 10 mld WTP at Kallissery, Construction of 35 mld capacity aerator at Kallissery including all channels,Renovation of 25 mld. Kallissery plant,Construction of Compound wall at Kallissery,Renovation of 33 mld. Thiruvalla plant,New Raw /Clear water pump sets at RW Pump house, CW pump house at Kallissery,Thirumoolapuram PH, Thiruvalla PH |
Status | On-going |
District | Pathanamthitta |
Executing Office | Adoor Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 73400000 |
TS Number | KWA/CE(SR)/PHTVL/2788/2016 Dtd. 23/01/2017 |
Technical specification | This package includes Construction of 10 mld WTP at Kallissery, Construction of 35 mld capacity aerator at Kallissery including all channels,Renovation of 25 mld. Kallissery plant,Construction of Compound wall at Kallissery,Renovation of 33 mld. Thiruvalla plant,New Raw /Clear water pump sets at RW Pump house, CW pump house at Kallissery,Thirumoolapuram PH, Thiruvalla PH |
Contractor | J&B ENGINEERING AND CONSTRUCTION COMPANY (Mob: 9447715266) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 28/05/2018 |
---|---|
Scheduled date of Completion as per agreement | 27 Sep 2019 |
Expected date of Completion | 31/10/2021 |
TS Date | 23 Jan 2017 |
---|---|
Estimate Approval | 01 Nov 2017 |
NIT Approval | 01 Nov 2017 |
Tender Closing | 30 Nov 2017 |
Technichal Pre-Qualification | 04 Dec 2017 |
Price bid opening | 04 Dec 2017 |
NA | 28 Mar 2018 |
---|---|
Workorder Date | 19 Mar 2018 |
Adoor Project Dn AE3 |
Date: 28/10/2021 |
Work has been completed | 100% Completed
completed.
Adoor Project Dn AE3 |
Date: 04/10/2021 |
Work has been completed | 100% Completed
100 % WORK COMPLETED EXCEPT GAUGE FITTING & BALANCE LANDSCAPPING.